INSP-Final Inspection | 5/9/2016 | 5/10/2016 | 5/10/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete. Activated irrigation timer, had water flowing from lawn sprinklers, opened inspectors test for water flow, after 27 seconds the exterior bell rang and the lawn irrigation shut off, providing all water flow to fire sprinkler inspectors test as notated on city approved drawings.
|
INSP-Final Inspection | 4/15/2016 | 4/15/2016 | 4/15/2016 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with Jeremy, phone number ###-####, not ready for final inspection.
|
INSP-Sprinkler Rough-in | 2/10/2016 | 2/11/2016 | 2/11/2016 | A | PASS |
Troy Cobbley
|
|
|
Rough-in and tenting passed. Piping can be covered. I noted that the pendant head just inside the Master Bedroom may be too close to the can light depending of light wattage. Riser was not built yet. No underground was inspected.
|
Sprinkler Plan Check | 2/2/2016 | | 2/2/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 2/2/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/2/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/2/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/2/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/2/2016 | | 2/2/2016 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 1/28/2016 | | 1/28/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 1/28/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 1/28/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 1/26/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/26/2016 | | 1/26/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 1/22/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 22 2016 3:09PM
|