INSP-Final Inspection | 12/16/2016 | 12/16/2016 | 12/16/2016 | P | PASS |
Jim Page
|
|
|
Final underground supply inspection passed/complete.
|
INSP-Supply line flush | 11/17/2016 | 11/22/2016 | 11/22/2016 | A | DONE |
Jim Page
|
|
|
Underground main supply flush complete
|
Telephone call | | | 11/17/2016 | | DONE |
|
|
|
Scott ok'd after hours inspection-called Brad to let know fees are in system and ready for them to pay
|
INSP-Sprinkler Rough-in/Hydro | 11/15/2016 | 11/15/2016 | 11/15/2016 | A | PASS |
Jim Page
|
|
|
Underground supply hydrostatic test complete
|
INSP-Sprinkler Rough-in | 5/26/2016 | 5/27/2016 | 5/27/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply passed/complete, underground approved for cover.
|
INSP-Sprinkler Rough-in | 5/26/2016 | 5/26/2016 | 5/26/2016 | P | PART |
Jim Page
|
|
|
Partial underground cover approved, thrustblocks will be poured at a later date, fittings requiring thrust blocks cannot be covered until thrustblocks are poured.
|
INSP-Sprinkler Rough-in | 2/23/2016 | 2/23/2016 | 2/23/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground stub only, approved for cover. Contractor will schedule inspection for rest of underground when completed.
|
Intake Approval | | | 1/26/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/26/2016 | | 1/26/2016 | | DONE |
Tim Frost
|
|
|
|
1st review completed | | | 1/26/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/26/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/26/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/26/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/26/2016 | | 1/26/2016 | | DONE |
Brittany Hill
|
|
|
|
Sprinkler Plan Check | 1/26/2016 | | 1/26/2016 | | PASS |
Tim Frost
|
|
|
|
Application received | | | 1/25/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 25 2016 1:14PM
|