INSP-Final Inspection | 5/20/2016 | 5/20/2016 | 5/20/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in | 3/8/2016 | 3/8/2016 | 3/8/2016 | P | CANC |
Jim Page
|
|
|
Inspection request was for the 4th floor hardlids, not the penthouse. This inspection request cancelled.
|
INSP-Sprinkler Rough-in/Hydro | 2/25/2016 | 2/26/2016 | 2/26/2016 | P | PASS |
Jim Page
|
|
|
Rough in inspection complete for penthouse, 2hr @ 200psi hydrostatic test complete for overhead sprinkler piping in penthouse.
|
Sprinkler Plan Check | 2/8/2016 | | 2/8/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/8/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/8/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/8/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/8/2016 | | 2/8/2016 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 2/5/2016 | | 2/5/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 2/5/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 2/5/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 2/4/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 2/4/2016 | | 2/4/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 2/3/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 3 2016 10:22AM
|