INSP-Final Inspection | 8/3/2016 | 8/4/2016 | 8/4/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete for level 9.
|
INSP-Sprinkler Rough-in/Hydro | 7/21/2016 | 7/22/2016 | 7/22/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for level 9, hydrostatic test complete for overhead fire sprinkler piping on level 9, tamper switch and flow switch satisfactorily tested for level 9.
|
INSP-Sprinkler Rough-in | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PASS |
Jim Page
|
|
|
Rough in inspection complete, a follow up RTC inspection will need to be scheduled after finish ceilings are complete for cover approval.
|
Intake Approval | | | 2/5/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 2/5/2016 | | 2/5/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/5/2016 | | 2/5/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 2/5/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/5/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/5/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/5/2016 | | 2/5/2016 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 2/3/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 3 2016 6:58PM
|