INSP-Final Inspection | 9/1/2016 | 9/2/2016 | 9/2/2016 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Seth Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 8/12/2016 | | DONE |
|
|
|
|
INSP-Final Inspection | 8/8/2016 | 8/9/2016 | 8/9/2016 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is ok for life safety with Scott's permission. I need as-builts, testing of elevator car #1 and the map at the facp.
|
Miscellaneous action | | | 8/9/2016 | | DONE |
|
|
|
EJ called to say he needs the work flow reopened to upload changes to floor plans & notification.
|
Plan Modification Accepted | | | 8/9/2016 | | |
|
|
|
Plan mod received for numerous design changes.
|
CHANGE STATUS TO (REV) | | | 8/9/2016 | | DONE |
|
|
|
Changed to review status for plan mod submittal.
|
Alarm Plan Check | 8/9/2016 | | 8/9/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/9/2016 | | DONE |
|
|
|
Plan mod approved. No additional review comments.
|
INSP-Alarm Testing | 8/5/2016 | 8/8/2016 | 8/8/2016 | A | DONE |
Troy Cobbley
|
|
|
Need data sheets, breaker locks and locations, test flow switches, test outside alarm bell, document box, map at the facp, test elevator recall
|
INSP-Final Inspection | 8/5/2016 | 8/5/2016 | 8/5/2016 | P | FAIL |
Troy Cobbley
|
|
|
Due to problems on the fire alarm system todays inspection was a walk through of the devices on the 4th and 3rd floors. I noted the need for as-builts due to added smoke detectors and the need for weather proof back boxes on the audio/visual devices installed in the restrooms with showers. Contractor did not have any of the small documents which included the data sheets and review notes.
|
Miscellaneous action | | | 3/3/2016 | | DONE |
|
|
|
Emailed EJ to let him know NAC calculations were not accurate. Requested he make corrections and submit them.
|
Alarm Plan Check | 3/3/2016 | | 3/3/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/3/2016 | | DONE |
|
|
|
Resubmittal approved with review comments.
|
Permit Ready to Issue | | | 3/3/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/3/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/3/2016 | | 3/3/2016 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 3/2/2016 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 2/11/2016 | | 2/11/2016 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 2/11/2016 | | FAIL |
|
|
|
See 1st review comments.
|
Miscellaneous action | | | 2/11/2016 | | DONE |
|
|
|
Emailed applicant the 1st plan review comments.
|
Application received | | | 2/9/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 9 2016 4:17PM
|