Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberFIR16-00089
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1099 W FRONT ST
Project NameSimplot Office Building
Customer Number 
ePlanReviewYes
Description
[Simplot World Headquarters - Levels 3 & 4]
The fire sprinkler scope of work consists of level 3 & 4 office building. The system will connect to the existing standpipes. New floor control valve will be added. A wet system shall be installed utilizing concealer style pendant sprinkler along with ssu's and intermediate level pendant sprinkler per NFPA 13 for light and ordinary hazards.
SIMPLOT OFFICE Tenant Improvement - This permit is to finish a new 306,345 square foot, nine-story office building for occupancy. The first floor will have a large lobby area, customer experience area and office and training areas. There will be a wellness center at the south end of the main building. Separate tenant improvement permits will be required to finish the future coffee shop, incubator space and future restaurant at the first floor of the annex. The second floor of the main building will be office space. The second floor of the annex will have a large lobby, a multipurpose assembly room and an auditorium. The third floor of the main building will be office space. The fourth floor of the main building will be office space. The fourth floor of the annex is a restaurant with a full kitchen and large exterior patio seating area. The fifth floor of the main building will be office space. The fifth floor of the annex has a kitchen, office areas and a greenhouse. The greenhouse structure is deferred and has not been reviewed or approved. The sixth floor will be office space with an exterior deck at the south end of the floor. The seventh floor will be office space with a large conference room, a kitchen and exterior decks at the east and west ends of the floor. The eighth floor will be office space. The ninth floor will be office space. The core areas were completed under the shell and core permit BLD14-02173. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/7/20173/7/20173/7/2017PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Final Inspection10/20/201610/20/201610/20/2016PPART
DetailsJim Page
Final fire sprinkler inspection for levels 3 & 4 complete. FIR permit will stay in issued status (Partial final for records) until BLD permit is ready to be finaled on life fire safety, at time of life fire safety completion FIR permit will be finaled as well.
Plan Modification Accepted  6/1/2016 DONE
Alarm Plan Check6/1/2016 6/1/2016 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  6/1/2016 DONE
Permit Ready to Issue  6/1/2016 DONE
plan mod ONLY
CHANGE STATUS TO (ISS)  6/1/2016 DONE
plan mod fees paid
INSP-Sprinkler Rough-in/Hydro5/10/20165/10/20165/10/2016APART
DetailsJim Page
Rough to cover inspection complete for level 4, level 4 approved for cover. 200 psi hydrostatic test complete for level 4.
INSP-Sprinkler Rough-in/Hydro5/6/20165/9/20165/9/2016ACANC
DetailsJim Page
Inspection request cancelled per coversation with point of contact on project. Rough-in/Hydro request will be rescheduled to coincide with early morning main line flush.
INSP-Sprinkler Rough-in4/18/20164/18/20164/18/2016PPART
DetailsJim Page
Partial rough to cover inspection complete for 3rd floor. Notated city approved plans area's that were inspected with red ink/yellow highlighter, area's notated on city approved drawings approved for cover.
Sprinkler Plan Check2/23/2016 2/23/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  2/23/2016 DONE
DetailsTim Frost
Permit Ready to Issue  2/23/2016 DONE
Issue and Print Permit  2/23/2016 DONE
Inspection Record Card- Fire2/23/2016 2/23/2016 DONE
DetailsChristina Prado
Sprinkler Plan Check2/17/2016 2/17/2016 FAIL
DetailsTim Frost
1st review completed  2/17/2016 FAIL
DetailsTim Frost
Miscellaneous action  2/17/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Intake Approval  2/12/2016 PASS
Plan assigned to (Tim)2/12/2016 2/12/2016 DONE
DetailsTim Frost
Application received  2/9/2016 DONE
Application submitted via PDS Online on Feb 9 2016 6:45PM