INSP-Final Inspection | 10/6/2017 | 10/6/2017 | 10/6/2017 | P | PASS |
Jim Page
|
|
|
Final inspection for this permit passed/complete.
|
INSP-Sprinkler Rough-in | 9/19/2017 | 9/19/2017 | 9/19/2017 | A | PASS |
Jim Page
|
|
|
Fire pump start up/flow test complete.
|
Sprinkler Plan Check | 4/20/2016 | | 4/20/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/20/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/20/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/20/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/20/2016 | | 4/20/2016 | | DONE |
Candy A. Nichols
|
|
|
|
Miscellaneous action | | | 3/11/2016 | | PEND |
|
|
|
Requested addional information via email. Project is on hold pending the information.
|
Sprinkler Plan Check | 3/2/2016 | | 3/2/2016 | | FAIL |
Tim Frost
|
|
|
Applicant requested the plan be denied. There are apparently more changes necessary. The review comments were minor and the project was going to be approved as noted.
|
Sprinkler Plan Check | 2/18/2016 | | 2/18/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 2/18/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 2/18/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 2/17/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 2/17/2016 | | 2/17/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 2/10/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 10 2016 2:58PM
|