INSP-Final Inspection | 6/1/2016 | 6/2/2016 | 6/2/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for level 4 passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 4/15/2016 | 4/15/2016 | 4/15/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for 4th floor, entire floor approved for cover. Overhead fire sprinkler hydrostatic test passed/complete.
|
INSP-Sprinkler Rough-in | 3/8/2016 | 3/8/2016 | 3/8/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for fire sprinkler piping above hardlids complete, notated city approved drawings with yellow highlighter and red ink the hardlids approved for cover.
|
Intake Approval | | | 2/17/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 2/17/2016 | | 2/17/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/17/2016 | | 2/17/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 2/17/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/17/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/17/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/17/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/17/2016 | | 2/17/2016 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 2/12/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 12 2016 10:15AM
|