INSP-Final Inspection | 6/1/2016 | 6/2/2016 | 6/2/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for level 3 passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 4/26/2016 | 4/27/2016 | 4/27/2016 | P | PASS |
Jim Page
|
|
|
Overhead rough to cover inspection complete for ceiling grid area's, all overhead fire sprinkler piping on level 3 approved for cover. 200 psi hydrostatic test passed/complete for level 3.
|
INSP-Sprinkler Rough-in | 3/17/2016 | 3/18/2016 | 3/18/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for hardlids on 3rd floor, hardlids on 3rd floor approved for cover.l
|
Intake Approval | | | 2/26/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 2/26/2016 | | 2/26/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/26/2016 | | 2/26/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 2/26/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/26/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/26/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/26/2016 | | 2/26/2016 | | DONE |
Brittany Hill
|
|
|
|
Application received | | | 2/17/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 17 2016 11:24AM
|