Permit Information
Permit NumberFIR16-00106
StatusFinaled
Name THORPE FIRE SPRINKLER SYSTEMS
Site Address 7640 W STATE ST
Project NameNorth Pointe #1
Customer Number 
ePlanReviewYes
Description
[North Pointe Retail Building 1 - Shell and Core]
The fire sprinkler scope of work consists of providing shell and core protection based on OH2. The system is designed as a grid layout with 2 ½” x 2 ½” x 1 ¼” pipe sizes. The new 4”x70’± C-900 underground with fittings and thrust blocks supplies a 3” backflow preventer with 3” riser.

(NORTH POINTE RETAIL – BLDG #1 – Shell and Core) Permit is to construct a 4,966 square foot Retail / Office / Assembly Shell building. This building is constructed as a wood frame building and a concrete footing. Work includes: new foundation, new exterior walls, new mechanical, stubbing in plumbing into the building, site work, new wood frame exterior walls, new manufactured wood truss roof system, and new electrical (Exterior Lighting Approved). This building will be fully Fire Sprinklered with an approved Fire Alarm system. System shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. NOTE: In accordance with Section C401.2 option #1 of the 2012 IECC; ANSI/ASHREA/IESNA 90.1 were used to show compliance with the Energy Code. The lighting installed within the tenant spaces shall also comply with ASHREA. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/13/20166/14/20166/14/2016PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Final Inspection6/13/20166/14/20166/13/2016ACANC
DetailsJim Page
Please call Jake when you are heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
INSP-Sprinkler Rough-in/Hydro4/28/20164/29/20164/29/2016APASS
DetailsJim Page
200 psi hydrostatic test for overhead fire sprinkler piping complete. Rough in inspection for shell protection complete, end of line sway bracing was not installed at time of inspection, end of line sway bracing install will be verified at final fire sprinkler inspection.
INSP-Sprinkler Rough-in/Hydro4/26/20164/28/20164/28/2016PCANC
DetailsJim Page
Call Jake when you are heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
INSP-Sprinkler Rough-in/Hydro4/20/20164/26/20164/26/2016PCANC
DetailsJim Page
Please call Jake when you are heading out. Thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
CHANGE STATUS TO (ISS)  4/18/2016 DONE
DetailsChristina Prado
Plan assigned to (Tim)4/14/2016 4/14/2016 DONE
DetailsTim Frost
Plan Modification Accepted  4/14/2016 DONE
Sprinkler Plan Check4/14/2016 4/14/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  4/14/2016 DONE
DetailsTim Frost
Permit Ready to Issue  4/6/2016 DONE
Issue and Print Permit  4/6/2016 DONE
Inspection Record Card- Fire4/6/2016 4/6/2016 DONE
DetailsChristina Prado
Sprinkler Plan Check4/4/2016 4/4/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  4/4/2016 DONE
DetailsTim Frost
Intake Approval  2/29/2016 PASS
Plan assigned to (Tim)2/29/2016 2/29/2016 DONE
DetailsTim Frost
Sprinkler Plan Check2/29/2016 2/29/2016 FAIL
DetailsTim Frost
Miscellaneous action  2/29/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
1st review completed  2/29/2016 FAIL
DetailsTim Frost
Application received  2/18/2016 DONE
Application submitted via PDS Online on Feb 18 2016 5:22PM