Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberFIR16-00118
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 400 S BROADWAY AVE
Project NameWGP 1 St. Luke's TI 2nd Floor
Customer Number 
ePlanReviewYes
Description
[WG Plaza1 Saint Luke's TI - Second Floor]
The fire sprinkler scope of work consists of remodeling the 2nd floor ONLY. The CPVC piping will be replaced with steel. The sprinklers in ceiling tile areas are on flex drops. Hydraulic calculations were provided for the sixth floor. This floor is similar enough; new calculations were not provided. The building plans examiner has indicated no changes are being performed on the atrium. The occupancy and use group are to remain the same.

(ST. LUKE'S)(MK PLAZA I - ENTIRE BUILDING) Remodel to entire high-rise building including basement and all 6 floors for new office tenant with some assembly uses per approved plans. Work to include demolition of existing tenant spaces on all floors and build back of new spaces on all floors to include new interior walls, doors, interior finish, new suspended ceilings, electrical work, mechanical work, plumbing work and fire protection equipment. Occupant load request for classrooms on 5th floor approved and attached to case. NOTE: This building is fully fire sprinklered for high-rise and atrium provisions. A smoke management system exists for the atrium.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/8/20166/10/20166/10/2016APASS
DetailsJim Page
Final fire sprinkler inspection for level 2 complete.
INSP-Final Inspection6/8/20166/9/20166/8/2016ACANC
DetailsJim Page
Jon Beazer is site contact Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
INSP-Sprinkler Rough-in/Hydro5/24/20165/25/20165/25/2016ACANC
DetailsJim Page
Inspection request was for basement level, this inspection request cancelled and a new inspection request generated.
INSP-Sprinkler Rough-in/Hydro5/6/20165/9/20165/9/2016PPASS
DetailsJim Page
200 psi hydrostatic test for overhead fire sprinkler piping located on level 2 complete.
INSP-Sprinkler Rough-in4/4/20164/6/20164/6/2016ACANC
DetailsJim Page
Duplicate inspection request, this request cancelled per conversation with point of contact, Jon phone number ###-####.
INSP-Sprinkler Rough-in/Hydro4/4/20164/5/20164/5/2016APART
DetailsTroy Cobbley
The 2nd floor piping above the hardlids/corridors is ok to cover. Rough-in passed.
INSP-Sprinkler Rough-in4/4/20164/4/20164/4/2016PCANC
DetailsTroy Cobbley
Rescheduled for tomorrow morning
Intake Approval  3/1/2016 PASS
Plan assigned to (Tim)3/1/2016 3/1/2016 DONE
DetailsTim Frost
Sprinkler Plan Check3/1/2016 3/1/2016 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  3/1/2016 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  3/1/2016 DONE
DetailsTim Frost
Permit Ready to Issue  3/1/2016 DONE
Issue and Print Permit  3/1/2016 DONE
Inspection Record Card- Fire3/1/2016 3/1/2016 DONE
DetailsChristina Prado
Application received  2/23/2016 DONE
Application submitted via PDS Online on Feb 23 2016 3:24PM