INSP-Final Inspection | 11/10/2016 | 11/10/2016 | 11/10/2016 | P | PASS |
Troy Cobbley
|
|
|
Tested functionality and reporting to panel. Engineered electrical plan sheet fire alarm design (special systems) onsite. Fire Alarm shop drawings need to be turned in by fire alarm contractor indentifying passagway notification, via as-built submittal.
|
INSP-Alarm Testing | 11/9/2016 | 11/9/2016 | 11/9/2016 | P | PART |
Troy Cobbley
|
|
|
Inspection and testing complete in commercial kitchen area of level 1a of GBAD.
|
Miscellaneous action | | | 10/28/2016 | | DONE |
|
|
|
Emailed Ken a copy of the approved alternate that requires notification in the breezeway between the district and Grove Hotel. Originally sent mid March of this year.
|
INSP-Final Inspection | 9/1/2016 | 9/1/2016 | 9/1/2016 | A | PART |
Jim Page
|
|
|
Final fire alarm inspection for level 4 fire of city center side of the building complete, level 4 of the convention center side of fire alarm system will be completed at a later date.
|
INSP-Final Inspection | 8/1/2016 | 8/3/2016 | 8/3/2016 | P | CANC |
Jim Page
|
|
|
Inspection request was for clearwater TI, this inspection request cancelled.
|
Telephone call | | | 6/15/2016 | | DONE |
|
|
|
Ken called to indicate he found that an additional sprinkler riser existed that he was not aware of during initial submittal. I informed him that changes of that size will require a plan mod and need to be submitted for review.
|
Plan resubmittals received | | | 3/16/2016 | | DONE |
|
|
|
|
Alarm Plan Check | 3/16/2016 | | 3/16/2016 | | PASS |
Lee G Meredith
|
|
|
Third review approved with review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 3/16/2016 | | DONE |
|
|
|
thrd submittal approved with review comments and requirements.
|
Permit Ready to Issue | | | 3/16/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/16/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/16/2016 | | 3/16/2016 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 3/11/2016 | | DONE |
|
|
|
Ken called regarding review #2 comments. He was sure that the 5th floor service corridor of the ballroom was open to the floor below and that the approved archtectural drawings were in error. I asked him to confirm this with the archtect and resubmit based on the results of that discussion. Also informed him that he needs to review and comply with the approved alternate for the walkway requirements for added weatherproof notification (BLD14-03207). Emailed him a copy of the approved alternate.
|
Alarm Plan Check | 3/9/2016 | | 3/9/2016 | | FAIL |
Lee G Meredith
|
|
|
See 2nd review comments.
|
Miscellaneous action | | | 3/9/2016 | | DONE |
|
|
|
Emailed 2nd review comments to Ken Webster.
|
Plan resubmittals received | | | 3/8/2016 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 3/7/2016 | | 3/7/2016 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 3/7/2016 | | FAIL |
|
|
|
Visible notification inadequate.
|
Miscellaneous action | | | 3/7/2016 | | DONE |
|
|
|
Emailed Ken a copy of the review comments.
|
Application received | | | 2/26/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 26 2016 11:24AM
|