Information based on query as of Friday, June 21, 2024.
Permit Information
Permit NumberFIR16-00129
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 421 E PARKCENTER BLVD
Project NameSAGE SCHOOL PHASE 2 TI
Customer Number 
ePlanReviewYes
Description
[Sage School Phase 2 TI]
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration. The existing hydraulic calculations appear to be adequate for the new use. The new flow test information is better than the original flow test.

This is a project is a change of occupancy therefore; the entire fire protection project shall meet current code. (Ref: IFC: 102.3)

(SAGE INTERNATIONAL SCHOOL – Phase II) This project is to convert the remainder of an existing covered mall building (Parkcenter Mall) into a new school. PLAN MODIFICATION - Plan mod to change a previously approved double door to a single 42 inch wide door due to structural constraints. 2-12-16 **TLW** The building is fire sprinklered for area increase. Under Phase I 30,0000 square feet of the Northern part of the building was built out (BLD14-00884). Under this phase the remaining 54,850 square feet will be built out with new classrooms, a library, cafeteria, and common area. Work is to include: [structural upgrades including: new wood sheer walls, new wood hold-downs, new drag sheer blocking and strapping, new wood headers, and concrete repairs], exterior site improvements, [construction of interior non-bearing walls to create 27 classrooms, 5 offices, 6 core restrooms, a staff room, two multipurpose assembly rooms, and a library], installation of new exterior windows, installation of a new roof on the entire structure, installation of accessible doors / hardware, installation of the second side of a two-hour wall assembly (first side completed in phase I), and interior finishes. NOTE: This permit fulfills the “Upgrade Agreement” on file for this building. When the building is finaled a request to nullify the existing “Upgrade Agreement” based on completion of this work should be submitted. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/28/20167/28/20167/28/2016PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Sprinkler Rough-in6/20/20166/20/20166/20/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping complete, notated area's approved for cover with pink highlighter/red ink on the city approved drawings, area's marked approved for cover.
INSP-Sprinkler Rough-in/Hydro6/3/20166/3/20166/3/2016PPART
DetailsJim Page
Notated area's inspected for rough to cover with pink highlighter/red ink on city approved drawings, area's marked with pink highlighter/red ink approved for cover.
INSP-Sprinkler Rough-in5/27/20165/27/20165/27/2016PPART
DetailsJim Page
Rough to cover inspection completed for multiple ceiling gridded area's, notated the city approved drawings with blue highlighter and red ink the area's approved for cover.
INSP-Sprinkler Rough-in5/16/20165/16/20165/16/2016PPART
DetailsJim Page
Notated area's inspected for rough to cover with yellow highlighter on city approved drawings, piping marked with yellow highlighter approved for cover.
INSP-Sprinkler Rough-in4/28/20164/28/20164/28/2016PPART
DetailsJim Page
Notated gridded area's approved for cover on the city approved drawings with blue highlighter. Area's marked are approved for cover.
INSP-Sprinkler Rough-in4/26/20164/26/20164/26/2016PPART
DetailsJim Page
Notated area's approved to cover with blue highlighter on city approved drawings, heads in hardlids marked blue with highlighter approved for cover.
INSP-Sprinkler Rough-in4/5/20164/5/20164/5/2016PPASS
DetailsJim Page
Rough to cover inspection for hardlids in restrooms complete, restrooms approved for cover.
INSP-Sprinkler Rough-in3/29/20163/29/20163/29/2016PPART
DetailsJim Page
Rough to cover inspection performed on soffit hardlids, soffit hardlids approved for cover.
Sprinkler Plan Check3/28/2016 3/28/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  3/28/2016 DONE
DetailsTim Frost
Permit Ready to Issue  3/28/2016 DONE
Issue and Print Permit  3/28/2016 DONE
Inspection Record Card- Fire3/28/2016 3/28/2016 DONE
DetailsCandy A. Nichols
Sprinkler Plan Check3/3/2016 3/3/2016 FAIL
DetailsTim Frost
1st review completed  3/3/2016 FAIL
DetailsTim Frost
Miscellaneous action  3/3/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Intake Approval  3/2/2016 PASS
Plan assigned to (Tim)3/2/2016 3/2/2016 DONE
DetailsTim Frost
Application received  2/29/2016 DONE
Application submitted via PDS Online on Feb 29 2016 8:20AM