Permit Information
Permit NumberFIR16-00131
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 4240 S ORCHARD ST
Project NameAlbertsons Boise Hangar
Customer Number 
ePlanReviewYes
Description
[Albertsons Boise Hangar]
The fire sprinkler scope of work consists of fully protecting the new Albertsons Boise Group II aircraft hangar, and office area per NFPA 13, NFPA 11, NFPA 20, NFPA 24, and NFPA 409. With two 80 psi 2000 gpm electric fire pumps one is back up, one wet pipe fire sprinkler systems, one 3% AFFF hand line system with two hose stations, and one 2% Jet-X High Expansion Foam system. The Alarm detection is by others.

The underground Fire Service has been previously permitted and installed under permit FIR15-00909

(ALBERTSON’S HANGAR) Permit is to construct a new 19,990 square foot Group II aircraft hangar. This building is fully fire sprinklered to comply with Ch. 4 Special Requirements for Aircraft Hangers. This building is complying with Interior Lighting for the required additional energy code package. The foundation and site work for this structure was permitted under BLD15-03897. Approval contingent upon adhering to the approved plans on file and attached engineering. Work to include: construction of new premanufactured metal building, installation of 2 hour UL rated exterior metal panels, new plumbing, new electrical, new mechanical, and interior finishes. This building will be fire sprinklered as required by section 412.4.6 in accordance with NFPA 409. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  7/21/2016 DONE
The foam test report and concentration graphs were supplied by TREASURE VALLEY FIRE PROTECTION today through Troy.

Based on the test report results 288 gal of foam would be required for the 12 minutes. The tank is 300 gal therefore, the supply of foam would appear to be adequate.

The concentration results were adequate per the supplied report.

Report and graphs are attached as documents.
INSP-Final Inspection7/20/20167/20/20167/20/2016PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection7/5/20167/7/20167/7/2016PPART
DetailsTroy Cobbley
Todays inspection was just for the jet-X 2% Foam Test. The system was activated by the smoke detectors and from time of smoke detector activation to discharge of foam was 5 seconds. The entire floor area to the walls and to a minimum depth of 2'-6" was achieved with-in 60 seconds. TVFP will provide documentation for the concentration, water flow and quantity of foam used. Also they need to provide the fire pump certification documents prior to a final sign off.
INSP-Final Inspection7/5/20167/8/20167/5/2016ACANC
DetailsTroy Cobbley
Jet-X 2% Foam Test 9:00am TVFP Foreman Kerry Turner Phone #: ###-#### >> Inspection requested via web by Christophe Wilson Inspection cancelled from web by: Christophe Wilson
INSP-Sprinkler Rough-in/Hydro6/27/20166/28/20166/28/2016APASS
DetailsTroy Cobbley
Remaining hydro tests passed. Pendants installed in Pump Room.
INSP-Sprinkler Rough-in6/27/20166/27/20166/27/2016PPASS
DetailsTroy Cobbley
Office area piping and pendants are complete. I noted one pendant head has been painted in the restroom accessible from the hanger. Heads in pump room not complete yet.
INSP-Supply line flush6/6/20166/10/20166/10/2016ACANC
DetailsTroy Cobbley
Rick Phone #: ###-####
INSP-Supply line flush6/6/20166/9/20166/9/2016PPASS
DetailsTroy Cobbley
Certification fo the two fire pumps passed today. Papaer work to be provided when finalized.
INSP-Sprinkler Rough-in/Hydro6/7/20166/8/20166/8/2016APASS
DetailsTroy Cobbley
The overhead hydros for Foam Gen. System, Wet Hanger, Hose System and the Test Header side of the Pump Room piping passed inspection.
INSP-Sprinkler Rough-in5/26/20165/26/20165/26/2016PPASS
DetailsTroy Cobbley
See the city approved plans for two pendant heads on the upper level that are ok for cover.
INSP-Conference5/17/20165/17/20165/17/2016PDONE
DetailsTroy Cobbley
After dicussing lack of slope in the FIre Pump Room with Scott Arellano I spoke to the project superintendant about the floor slope issue and that there would be no final sign off on the life safety until the floor had been sloped as per previous discussions.
INSP-Sprinkler Rough-in5/16/20165/17/20165/17/2016APASS
DetailsTroy Cobbley
Four pendant heads as marked on the drawings are ok for cover. I noted that the Fire Pump Room floor has not been sloped except for maybe a 1'-0" circle around the floor drain which is positioned next to the north wall. I spoke to the job superintendant again and deferred him to Scott Arellano.
INSP-Sprinkler Rough-in5/3/20165/3/20165/3/2016PPASS
DetailsTroy Cobbley
Pendant added in restroom. Piping is ok to cover
INSP-Sprinkler Rough-in4/28/20164/28/20164/28/2016PPART
DetailsTroy Cobbley
Rough-in for the Hanger area passed, just need bracing for the northwest foam diffusser finished up. General rough-in for the office area overhead piping is complete. Will need another rough-in inspection when all of the drops are cut/installed. Riser room/fire pump room is not complete. Need low point drain on the north main.
Permit Ready to Issue  4/13/2016 DONE
Issue and Print Permit  4/13/2016 DONE
Inspection Record Card- Fire4/13/2016 4/13/2016 DONE
DetailsChristina Prado
Sprinkler Plan Check4/12/2016 4/12/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  4/12/2016 DONE
DetailsTim Frost
Plan resubmittals received  3/24/2016 DONE
Sprinkler Plan Check3/24/2016 3/24/2016 FAIL
DetailsTim Frost
Miscellaneous action  3/24/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Early Start  3/22/2016 PASS
Sprinkler Plan Check3/8/2016 3/8/2016 FAIL
DetailsTim Frost
1st review completed  3/8/2016 FAIL
DetailsTim Frost
Miscellaneous action  3/8/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Intake Approval  3/4/2016 PASS
Plan assigned to (Tim)3/4/2016 3/4/2016 DONE
DetailsTim Frost
Application received  3/1/2016 DONE
Application submitted via PDS Online on Mar 1 2016 7:35AM