INSP-Final Inspection | 6/30/2016 | 7/1/2016 | 7/1/2016 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection passed/complete
|
INSP-Final Inspection | 6/13/2016 | 6/14/2016 | 6/14/2016 | P | PART |
Jim Page
|
|
|
Fire alarm inspection partially complete, tested/inspected waterflow, tampers, smoke detector above fire panel and pull station, HVAC units are over 2000cfm so HVAC untis require duct detectors with unit shutdown (induct detectors are shown on city approved drawings), HVAC units do not have power connected so duct detectors were INOP at time of inspection. Duct detectors need to be in operation or general contractor needs to have documentation from the city supporting the duct detectors being INOP.
|
Alarm Plan Check | 3/8/2016 | | 3/8/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/8/2016 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 3/8/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/8/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/8/2016 | | 3/8/2016 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 3/7/2016 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 3/2/2016 | | 3/2/2016 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 3/2/2016 | | FAIL |
|
|
|
See 1st review comments.
|
Miscellaneous action | | | 3/2/2016 | | DONE |
|
|
|
Emailed review comments to Damie.
|
Application received | | | 3/1/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 1 2016 9:29AM
|