INSP-Final Inspection | 12/12/2016 | 12/13/2016 | 12/13/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 11/28/2016 | 11/28/2016 | 11/28/2016 | P | PASS |
Jim Page
|
|
|
Overhead fire sprinkler hydrostatic test complete
|
INSP-Supply line flush | 11/18/2016 | 11/22/2016 | 11/22/2016 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete
|
INSP-Sprinkler Rough-in | 11/14/2016 | 11/15/2016 | 11/15/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in requested area complete, noted city approved drawings with pink highlighter/red ink area's approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 10/6/2016 | 10/6/2016 | 10/6/2016 | P | PASS |
Jim Page
|
|
|
Hydrostatic test complete for requested area, rough to cover inspection for overhead fire sprinkler piping in requested area complete, overhead fire sprinkler piping in requested area approved for cover.
|
INSP-Sprinkler Rough-in | 9/15/2016 | 9/15/2016 | 9/15/2016 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated the cuty approved drawings with blue highlighter overhead fire sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 8/15/2016 | 8/15/2016 | 8/15/2016 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings with blue highlighter and red ink overhead fire sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in | 8/11/2016 | 8/12/2016 | 8/11/2016 | A | CANC |
Jim Page
|
|
|
Inspection request rescheduled by me for 15AUG2016 per conversation with point of contact, Mike Phone #: ###-####
|
INSP-Sprinkler Rough-in | 6/29/2016 | 6/30/2016 | 6/30/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for underground supply, underground approved for cover.
|
INSP-Sprinkler Rough-in | 6/22/2016 | 6/22/2016 | 6/22/2016 | P | PART |
Jim Page
|
|
|
Rough to cover inspection complete for overhead fire sprinkler piping located in the southeast wing, notated area's approved to cover with green highlighter on the city approved drawings.
|
Permit Ready to Issue | | | 3/28/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/28/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/28/2016 | | 3/28/2016 | | DONE |
Candy A. Nichols
|
|
|
|
(F) Reprint permit | | | 3/28/2016 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/25/2016 | | 3/25/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/25/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/21/2016 | | 3/21/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 3/21/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 3/21/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 3/18/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/18/2016 | | 3/18/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 3/10/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 10 2016 1:16PM
|