INSP-Final Inspection | 5/10/2016 | 5/10/2016 | 5/10/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in | 4/5/2016 | 4/5/2016 | 4/5/2016 | P | PASS |
Jim Page
|
|
|
Overhead fire sprinkler tenting inspection passed/complete, overhead piping approved for cover.
|
INSP-Sprinkler Rough-in | 3/28/2016 | 3/28/2016 | 3/28/2016 | P | PART |
Jim Page
|
|
|
Rough in inspection complete, piping still needs tenting insulation installed. Piping cannot be covered until tenting inspection is performed and approved for cover.
|
Permit Ready to Issue | | | 3/28/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/28/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/28/2016 | | 3/28/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 3/22/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/22/2016 | | 3/22/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/22/2016 | | 3/22/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 3/22/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/22/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 3/17/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 17 2016 4:31PM
|