INSP-Final Inspection | 9/7/2017 | 9/7/2017 | 9/7/2017 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection completed on 17AUG2017
|
INSP-Sprinkler Rough-in/Hydro | 8/16/2017 | 8/17/2017 | 8/17/2017 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection for phase 1 passed/complete. Modifications to room 106 for ADA compliance and the addition of smoke detector in room 301 will be included on the as-builts for fire alarms.
|
INSP-Final Inspection | 8/16/2017 | 8/16/2017 | 8/16/2017 | P | CANC |
Jim Page
|
|
|
Rescheduled for 17AUG2017, this request is cancelled.
|
INSP-Final Inspection | 8/11/2017 | 8/11/2017 | 8/11/2017 | P | PART |
Jim Page
|
|
|
Final inspection for townhomes fire alarms and door release for floors 3, 4, 5 and 6 complete. Townhome number 106 is an ADA room, need audio and visual notification installed and inspected before room can be occupied.
|
INSP-Final Inspection | 6/16/2017 | 6/16/2017 | 6/16/2017 | A | PART |
Jim Page
|
|
|
Partial final fire alarm inspection complete for TCO requested area's, townhomes and door releases (magnetic door holders on west side doors for levels 3, 4, 5 and 6 not installed at time of inspection, these doors are not to be held open unless done by door release magnet) are the remaining items needing to be tested/inspected for fire alarms, these items will be scheduled for a later date,
|
INSP-Alarm Testing | 6/16/2017 | 6/16/2017 | 6/16/2017 | A | DONE |
Jim Page
|
|
|
Alarm testing c omplete for TCO requested area's
|
INSP-Alarm Testing | 6/15/2017 | 6/15/2017 | 6/15/2017 | P | PART |
Jim Page
|
|
|
Alarm testing performed on all fire sprinkler devices (all tamper switches excluding south standpipe control valve, this valve still needs to be wired to panel, will be locked in the open position until wiring is complete, fire pump power loss, all flow switches, high low air sensors and dry system pressure switches) Smoke/CO2 detectors were tested in units 601 and 602, devices were not going into alarm, alarm testing stopped until troubleshooting can be performed and issues corrected.
|
Plan resubmittals received | | | 3/31/2016 | | DONE |
|
|
|
|
Alarm Plan Check | 3/31/2016 | | 3/31/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/31/2016 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 3/31/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/31/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/31/2016 | | 3/31/2016 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 3/30/2016 | | |
|
|
|
Called Rand to inform him drawings were being returned due to numerous typo's and missing product data. Emailed review comments.
|
Plan assigned to (Lee) | 3/28/2016 | | 3/28/2016 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 3/28/2016 | | FAIL |
|
|
|
See first fire alarm review comments.
|
Application received | | | 3/25/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 25 2016 1:03PM
|