Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberFIR16-00227
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 2910 E AMITY RD
Project NameHayden Beverage Warehouse PHII
Customer Number 
ePlanReviewYes
Description
[Hayden Beverage Warehouse - Phase 2]
The fire sprinkler scope of work consists of demoing wet fire sprinkler system from the east and west areas of phase II remodel, install new Dry system in the New West 38 Degree Cooler, install new wet ESFR system in the new east 50 degree cooler, reconnect the existing middle portion of the building to the new supply piping, and relocate sprinklers in existing area to accommodate new wall and ceiling lay out. The new system and renaming existing system is to be supplied by the new Electric fire pump installed during phase I construction.

OWNER’S NOTE: The fire protection system design criteria used for this project, has the following restrictions:
• Plastic pallets are NOT permitted in the west cooler.
• The height of storage is limited to 25’ in both coolers.

(HAYDEN BEVERAGE) Phase 2 of the Hayden Beverage Relocation project. This portion of the building has 35,660 sq. ft. on the grade level and 8,000 sq. ft. on the second story. Work to include the construction of two walk in beverage coolers with the associated cooling units, a classroom, and a wine tasting room per the approved plans. Phase 1 of the project is being done under BLD15-04239. This is a fully fire sprinklered building for unlimited area. Any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 as regulated by the fire department. No racking is approved under this permit. A separate racking permit is required. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/14/20169/15/20169/15/2016PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete.
INSP-Sprinkler Rough-in/Hydro8/3/20168/3/20168/3/2016APASS
DetailsJim Page
24 hour air test for new dry system install passed/complete.
INSP-Sprinkler Rough-in/Hydro8/1/20168/2/20168/2/2016APART
DetailsJim Page
200 psi hydrostatic test complete, 24 hour air test started at 12:00 pm @ 40psi
INSP-Sprinkler Rough-in8/1/20168/1/20168/1/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located above ceiling grid area's complete, approved for cover.
INSP-Sprinkler Rough-in/Hydro5/6/20165/6/20165/6/2016PPASS
DetailsJim Page
Hydrostatic test complete for overhead wet system in northeast 50 degree cooler, hydrostatic test complete for dry system located northwest 38 degree cooler.
Permit Ready to Issue  4/18/2016 DONE
Issue and Print Permit  4/18/2016 DONE
Inspection Record Card- Fire4/18/2016 4/18/2016 DONE
DetailsCandy A. Nichols
Sprinkler Plan Check4/15/2016 4/15/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  4/15/2016 DONE
DetailsTim Frost
Sprinkler Plan Check4/8/2016 4/8/2016 FAIL
DetailsTim Frost
1st review completed  4/8/2016 FAIL
DetailsTim Frost
Miscellaneous action  4/8/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Intake Approval  4/5/2016 PASS
Plan assigned to (Tim)4/5/2016 4/5/2016 DONE
DetailsTim Frost
Application received  3/28/2016 DONE
Application submitted via PDS Online on Mar 28 2016 3:13PM