INSP-Final Inspection | 12/14/2016 | 12/15/2016 | 12/15/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in | 11/30/2016 | 12/6/2016 | 12/7/2016 | P | DONE |
Jim Page
|
|
|
Fire pump testing complete
|
INSP-Sprinkler Rough-in | 11/16/2016 | 11/17/2016 | 11/17/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, noted city approved drawings with red ink area's approved for cover.
|
INSP-Sprinkler Rough-in | 11/9/2016 | 11/10/2016 | 11/10/2016 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for Office area where piping is approved for cover. I noted two areas with wood located above the ceiling that will need to be addressed prior to a final sign off.
|
INSP-Sprinkler Rough-in/Hydro | 9/30/2016 | 10/4/2016 | 10/4/2016 | P | PASS |
Jim Page
|
|
|
24hr air test for dry system complete.
|
INSP-Sprinkler Rough-in/Hydro | 9/30/2016 | 10/3/2016 | 10/3/2016 | A | PART |
Jim Page
|
|
|
200psi hydrostatic test for all overhead fire sprinkler systems associated with this permit complete. 24 hour air test started at 11:00 am @ 40psi.
|
Permit Ready to Issue | | | 5/2/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/2/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/2/2016 | | 5/2/2016 | | DONE |
Candy A. Nichols
|
|
|
|
Sprinkler Plan Check | 4/27/2016 | | 4/27/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/13/2016 | | 4/13/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 4/13/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 4/13/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 4/12/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 4/12/2016 | | 4/12/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 4/6/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 6 2016 7:38AM
|