INSP-Final Inspection | 6/15/2016 | 6/15/2016 | 6/15/2016 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 5/18/2016 | 5/19/2016 | 5/19/2016 | A | FAIL |
Troy Cobbley
|
|
|
Tile been installed yet.
|
INSP-Final Inspection | 5/17/2016 | 5/18/2016 | 5/18/2016 | P | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow
|
INSP-Sprinkler Rough-in | 5/17/2016 | 5/18/2016 | 5/18/2016 | P | PASS |
Troy Cobbley
|
|
|
insulation has been corrected. Piping can be covered.
|
INSP-Final Inspection | 5/16/2016 | 5/17/2016 | 5/17/2016 | A | FAIL |
Troy Cobbley
|
|
|
Can't cover yet since insulation is still hanging down blocking the upright sprinkler heads in two locations. Also Don and I discussed the overspaced pendants in the Dining area. It looks like he will need to add two pendants to provide the required coverage.
|
INSP-Sprinkler Rough-in | 5/11/2016 | 5/12/2016 | 5/12/2016 | A | PART |
Troy Cobbley
|
|
|
General rough-in for the area inspected was ok except that there is deck mounted insulation that is hanging down and ubstructing the upright sprinkler heads and old partition walls that are also blocking upright sprinkler coverage. No piping is to be covered until these items are corrected and a re-inspection has taken place.
|
INSP-Sprinkler Rough-in | 4/20/2016 | 4/20/2016 | 4/20/2016 | P | CANC |
Troy Cobbley
|
|
|
Don Phone #: ###-####
|
INSP-Conference | 4/19/2016 | 4/19/2016 | 4/19/2016 | P | DONE |
Troy Cobbley
|
|
|
Don and I discussed the pendant sprinkler spacing in the dining room. I noted insulation at the roof deck blocking upright heads and possibly overspaced upright against draftstops that are not Dons scope of work but will need addressed prior to a cover inspection being done.
|
Permit Ready to Issue | | | 4/18/2016 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 4/18/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/18/2016 | | 4/18/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Sprinkler Plan Check | 4/14/2016 | | 4/14/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 4/14/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/14/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 4/12/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 12 2016 11:29AM
|