INSP-Final Inspection | 11/23/2016 | 11/29/2016 | 11/29/2016 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/15/2016 | 11/17/2016 | 11/17/2016 | A | FAIL |
Troy Cobbley
|
|
|
Could not test the alarms due to the sprinkler contractor not being there. Will need to reschedule.
|
INSP-Final Inspection | 8/1/2016 | 8/2/2016 | 8/2/2016 | A | CANC |
Troy Cobbley
|
|
|
Call to meet // CHRIS Phone #: ###-####
|
Plan assigned to (Lee) | 4/13/2016 | | 4/13/2016 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 4/13/2016 | | PASS |
|
|
|
|
Alarm Plan Check | 4/13/2016 | | 4/13/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 4/13/2016 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 4/13/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/13/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/13/2016 | | 4/13/2016 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 4/12/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 12 2016 1:14PM
|