INSP-Final Inspection | 10/10/2016 | 10/10/2016 | 10/10/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprimkler inspection for VRT passed/complete
|
INSP-Sprinkler Rough-in | 9/27/2016 | 9/29/2016 | 9/29/2016 | P | PASS |
Jim Page
|
|
|
200 psi hydrostatic test for VRT Dry Systems passed/complete.
|
INSP-Sprinkler Rough-in | 9/27/2016 | 9/28/2016 | 9/28/2016 | P | PASS |
Jim Page
|
|
|
24 hour air test for dry systems locared in the VRT section complete. Rough to cover inspection for all overhead fire sprinkler piping located VRT complete, all overhead fire sprinkler piping located in VRT approved for cover.
|
INSP-Final Inspection | 9/13/2016 | 9/19/2016 | 9/19/2016 | P | CANC |
Jim Page
|
|
|
No inspection request needed for today per conversation with Mike, phone number ###-####, this inspection request is cancelled.
|
INSP-Sprinkler Rough-in/Hydro | 9/13/2016 | 9/16/2016 | 9/16/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for overhead fire sprinkler piping located in VRT, overhead fire sprinkler piping located in VRT approved for cover.
|
Plan Modification Accepted | | | 9/16/2016 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 9/16/2016 | | 9/16/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/16/2016 | | 9/16/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/16/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/16/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/16/2016 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 9/14/2016 | 9/14/2016 | 9/14/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located above soffits in VRT complete, overhead fire sprinkler piping located above soffits in VRT approved for cover.
|
INSP-Sprinkler Rough-in | 9/9/2016 | 9/12/2016 | 9/12/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for west side drive through area & the southeast side ramp overhead fire sprinkler piping complete. Overhead fire sprinkler piping located in the west side drive through area & the southeast side ramp approved to cover. Rough to cover inspection for the fire sprinkler piping located above the ceilings in the central waiting/office area for VRT complete, overhead fire sprinkler piping in VRT waiting/office area approved for cover.
|
INSP-Sprinkler Rough-in | 8/16/2016 | 8/16/2016 | 8/16/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located above hardlids in VRT complete, overhead fire sprinkler piping above hardlids in VRT approved for cover.
|
INSP-Sprinkler Rough-in | 8/1/2016 | 8/2/2016 | 8/2/2016 | A | PART |
Jim Page
|
|
|
Rough to cover inspection complete for heads in soffit by main north stairs, need to verify proper installation for dry pendants in soffit area east of the main stairs.
|
Intake Approval | | | 4/21/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 4/21/2016 | | 4/21/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/21/2016 | | 4/21/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 4/21/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/21/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/21/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/21/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/21/2016 | | 4/21/2016 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 4/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 15 2016 4:04PM
|