INSP-Final Inspection | 4/13/2018 | 4/13/2018 | 4/13/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection per scope of work complete.
|
CHANGE STATUS TO (ISS) | | | 11/22/2017 | | DONE |
Christina Prado
|
|
|
Per Jim Page - change back to issue for further inspections
|
INSP-Final Inspection | 10/20/2017 | 10/20/2017 | 10/20/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work passed/complete.
|
INSP-Sprinkler Rough-in | 8/1/2016 | 8/1/2016 | 8/1/2016 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional area where sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 5/17/2016 | 5/18/2016 | 5/18/2016 | A | PASS |
Troy Cobbley
|
|
|
Work for phase 1 complete. Will need as-builts showing pipe routing changes as per discussion.
|
Intake Approval | | | 4/20/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 4/20/2016 | | 4/20/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/20/2016 | | 4/20/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 4/20/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/20/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/20/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/20/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/20/2016 | | 4/20/2016 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | | 4/19/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 19 2016 11:19AM
|