INSP-Final Inspection | 5/20/2016 | 5/23/2016 | 5/23/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in | 5/9/2016 | 5/10/2016 | 5/10/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, overhead fire sprinkler piping approved for cover. One fire sprinkler head was not installed at the receptionist area, will verify install at final inspection.
|
Intake Approval | | | 4/26/2016 | | |
|
|
|
|
Plan assigned to (Tim) | 4/26/2016 | | 4/26/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/26/2016 | | 4/26/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 4/26/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/26/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/26/2016 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 4/26/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/26/2016 | | 4/26/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Application received | | | 4/22/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 22 2016 6:09PM
|