INSP-Final Inspection | 9/30/2016 | 9/30/2016 | 9/30/2016 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 8/1/2016 | 8/2/2016 | 8/2/2016 | A | PART |
Troy Cobbley
|
|
|
Sprinkler work is complete in apartments 101,102, 201,202, 301, 302. (North end).
|
INSP-Final Inspection | 7/1/2016 | 7/5/2016 | 7/5/2016 | A | FAIL |
Troy Cobbley
|
|
|
This inspection is not for a final. But for approval for the tenting on the south half of the third floor. Piping can be covered.
|
Fees Due Hold | 6/15/2016 | | 7/1/2016 | | DONE |
Carlos Velazquez
|
|
|
|
INSP-Sprinkler Rough-in | 6/14/2016 | 6/15/2016 | 6/15/2016 | A | PASS |
Troy Cobbley
|
|
|
The tenting passed for the north half of the third floor. Piping for the north half of the third floor is ok to cover. Included piping crossing the breeze way.
|
INSP-Sprinkler Rough-in | 6/13/2016 | 6/14/2016 | 6/14/2016 | A | FAIL |
Troy Cobbley
|
|
|
Third floor tenting inspection failed again. I left a message on Pats voice mail describing what I saw and locations. Re-inspection fee applied.
|
INSP-Sprinkler Rough-in | 6/14/2016 | 6/14/2016 | 6/14/2016 | A | PASS |
Troy Cobbley
|
|
|
2nd and 3rd floor hydro tests passed
|
INSP-Sprinkler Rough-in/Hydro | 6/2/2016 | 6/3/2016 | 6/3/2016 | P | PART |
Troy Cobbley
|
|
|
1st floor hydro test passed. 2nd and 3rd failed due to visible loss of pressure at the guage.
|
INSP-Sprinkler Rough-in | 6/2/2016 | 6/3/2016 | 6/3/2016 | A | PASS |
Troy Cobbley
|
|
|
Second floor piping is now ok to cover. Third floor piping can not be covered since the tenting inspection failed again. Riser room can not be covered until tenting is addressed
|
INSP-Sprinkler Rough-in | 6/1/2016 | 6/1/2016 | 6/1/2016 | P | PART |
Troy Cobbley
|
|
|
1st floor north half piping is ok to cover. Tenting inspection failed. North half of the second floor can not be covered until the additional 90s and relocated heads in the remote area have been addressed with plan review. None of the third floor can be covered until the tenting inspection has passed. The insulation used for the tenting needs to be a minimum 38R.
|
Miscellaneous action | | | 6/1/2016 | | DONE |
|
|
|
Talked with Troy in regards to changes made on the second floor. The changes in this case does not affect the hydraulics or protection.
I followed up with Cam and made sure he knew it was causing project delays and problems when the fitters are making arbitrary field changes without approval first.
|
Plan Modification Accepted | | | 5/31/2016 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/31/2016 | | 5/31/2016 | | DONE |
Tim Frost
|
|
|
|
(F) Reprint permit | | | 5/31/2016 | | DONE |
|
|
|
|
INSP-Supply line flush | 5/26/2016 | 5/26/2016 | 5/26/2016 | P | CANC |
Troy Cobbley
|
|
|
Wrong permit number called in for underground flush
|
INSP-Sprinkler Rough-in | 5/19/2016 | 5/20/2016 | 5/20/2016 | P | PASS |
Troy Cobbley
|
|
|
The North half for the first and second floors rough-in passed and the piping can be covered. I also inspected the north half fo the third floor but it did not pass because no tenting had been performed and there are pipe routing changes and additional fittings and added heads that will need to be reviewed prior to a cover inspection being approved.
|
Sprinkler Plan Check | 5/5/2016 | | 5/5/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/5/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/5/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/5/2016 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 5/5/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/5/2016 | | 5/5/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Intake Approval | | | 5/4/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/4/2016 | | 5/4/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 4/24/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 24 2016 10:28AM
|