INSP-Final Inspection | 11/23/2016 | 11/28/2016 | 11/28/2016 | A | PASS |
Katie Marron
|
|
|
System tested satisfactory. Scope of work complete. Permit Finaled
|
INSP-Final Inspection | 11/22/2016 | 11/23/2016 | 11/23/2016 | A | CANC |
Katie Marron
|
|
|
During pretest it was found Bell is wired wrong. Will be rescheduled.
|
INSP-Final Inspection | 11/10/2016 | 11/14/2016 | 11/14/2016 | P | CANC |
Troy Cobbley
|
|
|
Call Anthony before heading out to confirm a time, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 11/9/2016 | 11/10/2016 | 11/10/2016 | P | CANC |
Katie Marron
|
|
|
Please call Anthony before you head out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Final Inspection | 11/2/2016 | 11/4/2016 | 11/4/2016 | P | CANC |
Katie Marron
|
|
|
Call Anthony before you head out, thank you! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
(F) Reprint permit | | | 11/2/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/2/2016 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 11/1/2016 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/1/2016 | | 11/1/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/1/2016 | | DONE |
|
|
|
|
Intake Approval | | | 10/27/2016 | | PASS |
|
|
|
|
Plan Modification Accepted | | | 10/27/2016 | | DONE |
|
|
|
|
Sprinkler Plan Check | 10/27/2016 | | 10/27/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 10/27/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
INSP-Sprinkler Rough-in | 9/13/2016 | 9/13/2016 | 9/13/2016 | P | DONE |
Katie Marron
|
|
|
Tenting inspection. At time of inspection, tenting completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 9/6/2016 | 9/6/2016 | 9/6/2016 | P | PASS |
Katie Marron
|
|
|
Hydrostatic re-test passed satisfactorily
|
INSP-Sprinkler Rough-in/Hydro | 9/1/2016 | 9/2/2016 | 9/2/2016 | P | FAIL |
Katie Marron
|
|
|
Roughin completed satisfactory. Hydrostatic test failed.
|
INSP-Sprinkler Rough-in/Hydro | 8/31/2016 | 9/1/2016 | 9/1/2016 | P | FAIL |
Jim Page
|
|
|
Contractor did not have overhead fire protection piping ready for hydrostatic test, hydro will need to be rescheduled for overhead fire sprinkler piping.
|
Permit Ready to Issue | | | 6/1/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/1/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/1/2016 | | 6/1/2016 | | DONE |
Kristal Soland
|
|
|
|
Miscellaneous action | | | 5/19/2016 | | DONE |
|
|
|
In lieu of having a second tank and pump the asst. FM aggreed to central station monitoring.
|
Sprinkler Plan Check | 5/19/2016 | | 5/19/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/19/2016 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 5/5/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/5/2016 | | 5/5/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/5/2016 | | 5/5/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 5/5/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 5/5/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 4/26/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 26 2016 8:20AM
|