Permit Information
Permit NumberFIR16-00305
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 500 S CAPITOL BLVD
Project NameINN @ 500
Customer Number 
ePlanReviewYes
Description
[Inn @ 500]
The fire sprinkler scope of work consists of a six level project per NFPA 13. Between level 1 and 2 there is has a two-hour horizontal separation. Level 1 is a parking garage based on OH 1. Levels 2-6 are based on light hazard. There are two wet manual Class I standpipes with outlets on the intermediate landings. The piping in the garage is in a conditioned space. The sprinklers in the garage are dry pendent type. There is a 500 Gpm @ 75 Psi fire pump located on the first level. The building is 62’-8” to the 6th level and is therefore is NOT classified as a high-rise. There is a fire code alternative on this project. (See building code review)

The underground was reviewed under permit FIR16-00054

(INN at 500 – Shell and Core / Hotel Interior Finish) Permit to finish and occupy all areas of this 90,000 square foot hotel building except a 3,320 square foot new restaurant area that will be submitted under a separate permit. This building is fire sprinklered for “R” occupancy provisions / alternate approval provisions / fire area provisions / etc. This building utilizes enhanced lighting to comply with the 2012 IECC. Scope of work includes: installation of rated assemblies (corridors / type of construction separations / distance to property line separations / rated shafts), [interior non-bearing partitions creating 111 guest rooms, lobby area, restaurant area, trash room, mechanical storage room, bike storage room, two meeting rooms, office area, fitness center, and laundry / storage room], new electrical, new plumbing, new mechanical, new interior / exterior finishes, new accessible doors / hardware, and related site work. This building is fully fire sprinklered and alarmed. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/8/20172/8/20172/8/2017PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Final Inspection2/2/20172/2/20172/2/2017PPART
DetailsJim Page
Final inspection for level 6 complete
Miscellaneous action  1/30/2017 DONE
Spoke with Brad today. We have agreeded on changing the level of the laundry shoot sprinklers. Brad, will send an As Built Drawing at the end of the project.
INSP-Final Inspection1/13/20171/13/20171/13/2017APART
DetailsJim Page
Final fire sprinkler inspection for levels 1 through 4 complete. Tamper and flow switch inspections complete for levels 1 through 6.
INSP-Sprinkler Rough-in/Hydro1/5/20171/6/20171/6/2017APASS
DetailsTroy Cobbley
Hydro test for the 6th floor passed.
INSP-Sprinkler Rough-in12/23/201612/27/201612/27/2016APASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping in corridors and drop ceilings in rooms on level 6 complete, main corridors and drop ceilings in rooms approved for cover.
INSP-Sprinkler Rough-in/Hydro12/23/201612/27/201612/27/2016APASS
DetailsJim Page
4th floor and 5th floor hydrostatic test for overhead fire sprinkler piping complete
INSP-Final Inspection12/16/201612/16/201612/16/2016PPART
DetailsJim Page
Partial final complete for phased occupancy on the overhead fire sprinklers. Items completed are the fire pump room, pump commissioning, east and west standpipes, levels 1, 2 and 3, tampers and flow switches for mentioned area's passed/complete. Remaining area's for overhead fire sprinklers will be inspected at a later date when completed.
INSP-Sprinkler Rough-in/Hydro12/14/201612/15/201612/15/2016PPART
DetailsJim Page
Hydrostatic test complete for levels 1, 2 and 3 as well as west standpipe.
INSP-Sprinkler Rough-in12/13/201612/14/201612/14/2016APASS
DetailsJim Page
Rough to cover inspection for pendant heads located in drive through area on level 1 complete, area mentioned approved for cover.
INSP-Sprinkler Rough-in/Hydro12/12/201612/13/201612/13/2016ADONE
DetailsJim Page
Fire pump commissioning complete.
INSP-Sprinkler Rough-in12/9/201612/9/201612/9/2016APART
DetailsJim Page
Partial rough to cover complete for level 1 parking area, cover approved from fire pump room to the east wall on level 1.
INSP-Sprinkler Rough-in12/5/201612/5/201612/5/2016APART
DetailsJim Page
Cover inspection for pendant heads in garage area complete from east side to column lin 6.5, area in parking garage up to column 6.5 approved for cover.
INSP-Sprinkler Rough-in/Hydro11/14/201611/15/201611/15/2016APART
DetailsJim Page
Rough to cover inspectio for overhead fire sprinkler piping located above the ceiling grid on level 2 complete, overhead fire sprinkler piping located above ceiling grid on level 2 spproved for cover. Partial tenting inspection for fire sprinkler piping located on level 6 complete, notated city approved drawings areas approved for cover.
Sprinkler Plan Check10/28/2016 10/28/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  10/28/2016 DONE
DetailsTim Frost
(F) Reprint permit  10/28/2016 DONE
CHANGE STATUS TO (ISS)  10/28/2016 DONE
Plan Mod. No fees due per Tim Frost
INSP-Sprinkler Rough-in9/22/20169/23/20169/23/2016APASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located on level 5 complete, overhead fire sprinkler piping located on level 5 approved for cover.
INSP-Sprinkler Rough-in9/22/20169/22/20169/22/2016PCANC
DetailsTroy Cobbley
Per discussion with Adam this is rescheduled for tomorrow morning
INSP-Sprinkler Rough-in9/9/20169/9/20169/9/2016PPASS
DetailsJim Page
Rough to cover inspection for requested area's on level 1 west side complete, notated city approved drawings with pink highlighter area's inspected and approved for cover.
INSP-Sprinkler Rough-in9/2/20169/2/20169/2/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located on level 4 west complete, notated city approved drawings with green highlighter fire sprinkler piping area's that are approved for cover.
INSP-Sprinkler Rough-in8/24/20168/25/20168/25/2016APASS
DetailsJim Page
Partial rough to cover inspection complete for overhead fire sprinkler piping on levels 2, 3 and 4. Notated the city approved drawings with green highlighter overhead fire sprinkler piping approved for cover.
INSP-Sprinkler Rough-in7/27/20167/28/20167/28/2016APART
DetailsJim Page
Partial rough to cover inspection for overhead fire sprinkler piping located on level 3 complete, notated the city approved drawings with pink highlighter/red ink area's approved for cover.
INSP-Sprinkler Rough-in7/13/20167/13/20167/13/2016PPART
DetailsJim Page
Partial rough to cover complete for level 2 overhead fire sprinkler piping, notated the city approved drawings with blue highlighter/red ink, the overhead fire sprinkler piping approved for cover.
INSP-Sprinkler Rough-in6/24/20166/27/20166/27/2016APART
DetailsJim Page
Pre-set hangers on level 2 west as well as northwest side approved for cover. Rough to cover inspection complete for level 1 west side overhead fire sprinkler piping, notated city approved drawings with green highlighter & red ink area's approved for cover.
Miscellaneous action  5/26/2016 PEND
*** FIELD INSPECTOR ***
During the fire pump acceptance test a certified pumo curve is to be supplied.

NFPA 20, 4.5.1 Certified shop test curves showing head capacity and brake horsepower of the pump shall be furnished by the
manufacturer to the purchaser.

NFPA 20, 4.5.2 The purchaser shall furnish the data required in 4.5.1 to the authority having jurisdiction.
Sprinkler Plan Check5/26/2016 5/26/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  5/26/2016 DONE
DetailsTim Frost
Permit Ready to Issue  5/26/2016 DONE
Issue and Print Permit  5/26/2016 DONE
Inspection Record Card- Fire5/26/2016 5/26/2016 DONE
DetailsCandy A. Nichols
Intake Approval  5/16/2016 PASS
Plan assigned to (Tim)5/16/2016 5/16/2016 DONE
DetailsTim Frost
Miscellaneous action  5/16/2016 DONE
Horizontal Exits
The fire code plan review mentions horizontal exits. Per the building code plan reviewer there are no longer and horizontal exits on this project.
Sprinkler Plan Check5/16/2016 5/16/2016 FAIL
DetailsTim Frost
1st review completed  5/16/2016 FAIL
DetailsTim Frost
Miscellaneous action  5/16/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  5/2/2016 DONE
Application submitted via PDS Online on May 2 2016 2:15PM