INSP-Final Inspection | 2/8/2017 | 2/8/2017 | 2/8/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 2/2/2017 | 2/2/2017 | 2/2/2017 | P | PART |
Jim Page
|
|
|
Final inspection for level 6 complete
|
Miscellaneous action | | | 1/30/2017 | | DONE |
|
|
|
Spoke with Brad today. We have agreeded on changing the level of the laundry shoot sprinklers. Brad, will send an As Built Drawing at the end of the project.
|
INSP-Final Inspection | 1/13/2017 | 1/13/2017 | 1/13/2017 | A | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for levels 1 through 4 complete. Tamper and flow switch inspections complete for levels 1 through 6.
|
INSP-Sprinkler Rough-in/Hydro | 1/5/2017 | 1/6/2017 | 1/6/2017 | A | PASS |
Troy Cobbley
|
|
|
Hydro test for the 6th floor passed.
|
INSP-Sprinkler Rough-in | 12/23/2016 | 12/27/2016 | 12/27/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in corridors and drop ceilings in rooms on level 6 complete, main corridors and drop ceilings in rooms approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 12/23/2016 | 12/27/2016 | 12/27/2016 | A | PASS |
Jim Page
|
|
|
4th floor and 5th floor hydrostatic test for overhead fire sprinkler piping complete
|
INSP-Final Inspection | 12/16/2016 | 12/16/2016 | 12/16/2016 | P | PART |
Jim Page
|
|
|
Partial final complete for phased occupancy on the overhead fire sprinklers. Items completed are the fire pump room, pump commissioning, east and west standpipes, levels 1, 2 and 3, tampers and flow switches for mentioned area's passed/complete. Remaining area's for overhead fire sprinklers will be inspected at a later date when completed.
|
INSP-Sprinkler Rough-in/Hydro | 12/14/2016 | 12/15/2016 | 12/15/2016 | P | PART |
Jim Page
|
|
|
Hydrostatic test complete for levels 1, 2 and 3 as well as west standpipe.
|
INSP-Sprinkler Rough-in | 12/13/2016 | 12/14/2016 | 12/14/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for pendant heads located in drive through area on level 1 complete, area mentioned approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2016 | 12/13/2016 | 12/13/2016 | A | DONE |
Jim Page
|
|
|
Fire pump commissioning complete.
|
INSP-Sprinkler Rough-in | 12/9/2016 | 12/9/2016 | 12/9/2016 | A | PART |
Jim Page
|
|
|
Partial rough to cover complete for level 1 parking area, cover approved from fire pump room to the east wall on level 1.
|
INSP-Sprinkler Rough-in | 12/5/2016 | 12/5/2016 | 12/5/2016 | A | PART |
Jim Page
|
|
|
Cover inspection for pendant heads in garage area complete from east side to column lin 6.5, area in parking garage up to column 6.5 approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 11/14/2016 | 11/15/2016 | 11/15/2016 | A | PART |
Jim Page
|
|
|
Rough to cover inspectio for overhead fire sprinkler piping located above the ceiling grid on level 2 complete, overhead fire sprinkler piping located above ceiling grid on level 2 spproved for cover. Partial tenting inspection for fire sprinkler piping located on level 6 complete, notated city approved drawings areas approved for cover.
|
Sprinkler Plan Check | 10/28/2016 | | 10/28/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/28/2016 | | DONE |
Tim Frost
|
|
|
|
(F) Reprint permit | | | 10/28/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/28/2016 | | DONE |
|
|
|
Plan Mod. No fees due per Tim Frost
|
INSP-Sprinkler Rough-in | 9/22/2016 | 9/23/2016 | 9/23/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located on level 5 complete, overhead fire sprinkler piping located on level 5 approved for cover.
|
INSP-Sprinkler Rough-in | 9/22/2016 | 9/22/2016 | 9/22/2016 | P | CANC |
Troy Cobbley
|
|
|
Per discussion with Adam this is rescheduled for tomorrow morning
|
INSP-Sprinkler Rough-in | 9/9/2016 | 9/9/2016 | 9/9/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for requested area's on level 1 west side complete, notated city approved drawings with pink highlighter area's inspected and approved for cover.
|
INSP-Sprinkler Rough-in | 9/2/2016 | 9/2/2016 | 9/2/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located on level 4 west complete, notated city approved drawings with green highlighter fire sprinkler piping area's that are approved for cover.
|
INSP-Sprinkler Rough-in | 8/24/2016 | 8/25/2016 | 8/25/2016 | A | PASS |
Jim Page
|
|
|
Partial rough to cover inspection complete for overhead fire sprinkler piping on levels 2, 3 and 4. Notated the city approved drawings with green highlighter overhead fire sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in | 7/27/2016 | 7/28/2016 | 7/28/2016 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping located on level 3 complete, notated the city approved drawings with pink highlighter/red ink area's approved for cover.
|
INSP-Sprinkler Rough-in | 7/13/2016 | 7/13/2016 | 7/13/2016 | P | PART |
Jim Page
|
|
|
Partial rough to cover complete for level 2 overhead fire sprinkler piping, notated the city approved drawings with blue highlighter/red ink, the overhead fire sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in | 6/24/2016 | 6/27/2016 | 6/27/2016 | A | PART |
Jim Page
|
|
|
Pre-set hangers on level 2 west as well as northwest side approved for cover. Rough to cover inspection complete for level 1 west side overhead fire sprinkler piping, notated city approved drawings with green highlighter & red ink area's approved for cover.
|
Miscellaneous action | | | 5/26/2016 | | PEND |
|
|
|
*** FIELD INSPECTOR ***
During the fire pump acceptance test a certified pumo curve is to be supplied.
NFPA 20, 4.5.1 Certified shop test curves showing head capacity and brake horsepower of the pump shall be furnished by the
manufacturer to the purchaser.
NFPA 20, 4.5.2 The purchaser shall furnish the data required in 4.5.1 to the authority having jurisdiction.
|
Sprinkler Plan Check | 5/26/2016 | | 5/26/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/26/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/26/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/26/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/26/2016 | | 5/26/2016 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 5/16/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/16/2016 | | 5/16/2016 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 5/16/2016 | | DONE |
|
|
|
Horizontal Exits
The fire code plan review mentions horizontal exits. Per the building code plan reviewer there are no longer and horizontal exits on this project.
|
Sprinkler Plan Check | 5/16/2016 | | 5/16/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 5/16/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 5/16/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 5/2/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 2 2016 2:15PM
|