INSP-Final Inspection | 1/12/2017 | 1/13/2017 | 1/13/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/6/2017 | 1/10/2017 | 1/10/2017 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for a final inspection due to fire alarm issues. However the rough-in passed.
|
INSP-Final Inspection | 12/30/2016 | 1/6/2017 | 1/6/2017 | A | CANC |
Troy Cobbley
|
|
|
Troy Nelson is our foreman ###-#### Phone #: ###-#### >> Inspection requested via web by Brad Bettencourt Inspection cancelled from web by: Brad Bettencourt
|
INSP-Sprinkler Rough-in | 11/10/2016 | 11/10/2016 | 11/10/2016 | P | CANC |
Troy Cobbley
|
|
|
Please call Troy Nelson with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
Sprinkler Plan Check | 5/23/2016 | | 5/23/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/23/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/23/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/23/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/23/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/23/2016 | | 5/23/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 5/17/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/17/2016 | | 5/17/2016 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 5/17/2016 | | PEND |
|
|
|
On hold pending approval of detection drawings
|
Application received | | | 5/4/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 4 2016 10:56AM
|