INSP-Final Inspection | 9/6/2016 | 9/7/2016 | 9/7/2016 | A | PASS |
Jim Page
|
|
|
Previously noted items have been repaired/addressed, final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 6/13/2016 | 6/13/2016 | 6/13/2016 | P | FAIL |
Troy Cobbley
|
|
|
Resubmit hydraulic calculations to plan review showing the additional eight 3" 90's and pipe routing changes, provide sprinkler coverage under the combustible stairs (not shown on plans) per NFPA 8.15, two of the new branchlines appear to be blocked by 12" beams and 8" z-purlins, provide missing 4-way brace at the old anti-freeze loop location as per plans.
|
(F) Reprint permit | | | 6/13/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/13/2016 | | 6/13/2016 | | DONE |
Brittany Hill
|
|
|
|
Issue and Print Permit | | | 6/13/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/31/2016 | | DONE |
|
|
|
all requirments met
|
Inspection Record Card- Fire | 5/31/2016 | | 5/31/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Sprinkler Plan Check | 5/27/2016 | | 5/27/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/27/2016 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 5/17/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/17/2016 | | 5/17/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/17/2016 | | 5/17/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 5/17/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 5/17/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 5/6/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 6 2016 9:20AM
|