Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberFIR16-00314
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 1257 W RIVER ST
Project NameRiver Street Mixed Use Buildin
Customer Number 
ePlanReviewYes
Description
[River Street Mixed Use Building]
The fire sprinkler scope of work consists of a four level building protected per NFPA 13. The building is mixed use with mercantile on the first level, office on the second level and levels 3 & 4 are dormitory. The building does not have an attic and is framed with composite wood joists filled with noncombustible insulation. There are floor control and standpipe isolation valves. The system is supply by 6”x 73’+- C-900 underground piping through a4” backflow preventer with a 4” header. Piping on the first floor is steel with the remainder of the piping being CPVC.

Permit is to complete an interior build out of a 4 story 16,581 square foot multi use building. The first floor will be a vanilla finish of two office suites, the second floor is a common area and two apartments, the third and fourth floor are dormitories for high school exchange students. This building will be fire sprinklered for height increase and residential occupancies (A compliant NFPA 13 is required). Approval contingent upon adhering to the approved plans on file and attached engineering. Work to include: [Construction of interior non-bearing walls to create two office suites, two interior exit stairways, two apartments, common area (kitchen / living room, dining area), 18 dorm rooms, two common shower rooms, two laundry rooms, and accessory spaces), new electrical (reduced interior lighting to comply with Additional Efficiency Option), new mechanical, new appliances, new plumbing, and interior finishes in compliance with chapter 8 of the 2012 IBC. This building’s super structure was permitted under BLD15-04329 and the foundation permit was pulled under BLD15-04236. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/6/20169/7/20169/7/2016APASS
DetailsJim Page
Final fire sprinkler inspection passed/complete, noted that fire sprinkler riser room signage will be installed when painting on door is complete.
INSP-Sprinkler Rough-in/Hydro8/24/20168/25/20168/25/2016APASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping on level 1 complete, level 1 overhead fire sprinkler piping approved for cover. Hydrostatic test for overhead fire sprinkler throughout building complete.
INSP-Sprinkler Rough-in7/18/20167/19/20167/19/2016APASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping on level 2 complete, level 2 overhead fire sprinkler piping approved for cover.
INSP-Sprinkler Rough-in7/11/20167/11/20167/11/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping on level 3 complete, level 3 overhead fire sprinkler piping approved for cover.
INSP-Sprinkler Rough-in7/1/20167/1/20167/1/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located on level 4 complete, overhead fire sprinkler piping on level 4 approved for cover.
Permit Ready to Issue  6/13/2016 DONE
Issue and Print Permit  6/13/2016 DONE
Inspection Record Card- Fire6/13/2016 6/13/2016 DONE
DetailsCandy A. Nichols
Sprinkler Plan Check6/9/2016 6/9/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  6/9/2016 DONE
DetailsTim Frost
Sprinkler Plan Check5/18/2016 5/18/2016 FAIL
DetailsTim Frost
1st review completed  5/18/2016 FAIL
DetailsTim Frost
Miscellaneous action  5/18/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Intake Approval  5/17/2016 PASS
Plan assigned to (Tim)5/17/2016 5/17/2016 DONE
DetailsTim Frost
Application received  5/6/2016 DONE
Application submitted via PDS Online on May 6 2016 3:11PM