INSP-Final Inspection | 9/6/2016 | 9/6/2016 | 9/6/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 8/11/2016 | 8/11/2016 | 8/12/2016 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations signed and dated where piping is ok to cover.
|
INSP-Sprinkler Rough-in | 7/29/2016 | 8/1/2016 | 8/1/2016 | A | PASS |
Troy Cobbley
|
|
|
This inspection is for the pharmacy. Piping is ok to cover.
|
INSP-Sprinkler Rough-in | 5/25/2016 | 5/25/2016 | 5/25/2016 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for heads added to offices in and by electronics, notated the city approved drawings with red ink the heads that are approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 5/20/2016 | 5/23/2016 | 5/23/2016 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was just for two heads in hard lids but there were no approved plans on site. I also noted wood bracing above the future ceiling that is installed in a space with no upright sprinkler protection that will have to be addressed prior to a cover inspection.
|
Intake Approval | | | 5/10/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/10/2016 | | 5/10/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/10/2016 | | 5/10/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/10/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/10/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/10/2016 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 5/10/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/10/2016 | | 5/10/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Application received | | | 5/9/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 9 2016 10:42AM
|