INSP-Final Inspection | 1/11/2017 | 1/11/2017 | 1/11/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Final Inspection | 12/30/2016 | 1/4/2017 | 1/4/2017 | P | CANC |
Jim Page
|
|
|
Could not test level 2 due to a cut pipe, cut to piping was made after hydrostatic test. Alarm inspection failed due to sync issues on level 4, cannot perform final inspection on fire sprinklers until fire alarm issue is resolved.
|
INSP-Supply line flush | 11/29/2016 | 11/30/2016 | 11/30/2016 | P | DONE |
Katie Marron
|
|
|
supply line flush completed
|
INSP-Supply line flush | 11/28/2016 | 11/29/2016 | 11/29/2016 | P | CANC |
Scott Arellano
|
|
|
Suez Water is scheduled to do the flush at 1pm. Please call Jake if there is a conflict. Thank you! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 10/12/2016 | 10/13/2016 | 10/13/2016 | P | CANC |
Jim Page
|
|
|
Please call Jake when you are headed out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in | 9/19/2016 | 9/20/2016 | 9/20/2016 | P | PASS |
Jim Page
|
|
|
Tenting inspection for fire sprinkler piping in attic spaces on level 4 and level 3 complete. Overhead fire sprinkler piping/tenting on level 3 and 4 approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 9/13/2016 | 9/14/2016 | 9/14/2016 | A | PASS |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping located on levels 1, 2, 3 and 4 complete. Rough to cover inspection for overhead fire sprinkler piping complete, levels 1 and 2 approved for cover. Partial cover approved for level 3, fire sprinkler piping located in attic spaces cannot be covered until tenting inspection is complete, all of level 4 not approved for cover until tenting inspection is complete.
|
INSP-Sprinkler Rough-in/Hydro | 8/23/2016 | 8/24/2016 | 8/24/2016 | P | FAIL |
Jim Page
|
|
|
Overhead fire sprinkler piping not ready for hydrostatic test, multiple leaks throughout the sprinkler system. Hydrostatic test will need to be rescheduled after repairs are made.
|
INSP-Sprinkler Rough-in/Hydro | 8/17/2016 | 8/17/2016 | 8/17/2016 | P | PASS |
Jim Page
|
|
|
200 psi hydrostatic test for standpipe complete
|
INSP-Supply line flush | 7/20/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Jim Page
|
|
|
Inspection request was for underground hydrostatic test and underground rough to cover, not a flush. Underground hydrostatic test passed/complete, underground supply approved for cover, flush will be completed at a later date.
|
INSP-Supply line flush | 7/20/2016 | 7/21/2016 | 7/20/2016 | A | CANC |
Jim Page
|
|
|
Underground rough inspection. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
Permit Ready to Issue | | | 5/26/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/26/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/26/2016 | | 5/26/2016 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 5/24/2016 | | 5/24/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/24/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2016 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 5/23/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/23/2016 | | 5/23/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 5/10/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 10 2016 11:17PM
|