INSP-Final Inspection | 6/9/2016 | 6/10/2016 | 6/9/2016 | A | PASS |
Jim Page
|
|
|
Inspection request for fire alarm final was completed on June 8th, inspection was requested as a rough in and not a final inspection. Final fire alarm inspection passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 6/8/2016 | 6/8/2016 | 6/8/2016 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection complete.
|
INSP-Conference | 6/2/2016 | 6/2/2016 | 6/2/2016 | P | DONE |
Troy Cobbley
|
|
|
The interconnect with the hood suppression system was tested under FIR16-00287 but was not verified at the monitoring company.
|
Application received | | | 5/11/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 11 2016 11:09AM
|
Plan assigned to (Lee) | 5/11/2016 | | 5/11/2016 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 5/11/2016 | | PASS |
|
|
|
|
Alarm Plan Check | 5/11/2016 | | 5/11/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 5/11/2016 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 5/11/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/11/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/11/2016 | | 5/11/2016 | | DONE |
Candy A. Nichols
|
|
|
|