INSP-Final Inspection | 8/11/2017 | 8/14/2017 | 8/14/2017 | A | PASS |
Jim Page
|
|
|
Previously noted items have been repaired, final fire alarm inspection for area of work passed/complete.
|
INSP-Alarm Testing | 11/16/2016 | 11/17/2016 | 11/17/2016 | A | PART |
Troy Cobbley
|
|
|
New notification devices functioned correctly in the new scope of work. The issues is the new devices do not sync with the existing devices outside of the scope of work. I contacted Ron with the Boise Fire Dept and he stated that the new and old devices will need to sync as per code requirements.
|
INSP-Alarm Testing | 10/19/2016 | 10/20/2016 | 10/20/2016 | A | PART |
Troy Cobbley
|
|
|
For a final sign off the new notification devices need to be installed and tested. Per Scott Arellano a 30 temporary for life safety is ok until the new devices are installed and tested.
|
CHANGE STATUS TO (ISS) | | | 10/17/2016 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 10/14/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (REV) | | | 10/14/2016 | | DONE |
|
|
|
|
1st review completed | | | 10/14/2016 | | PASS |
|
|
|
|
Alarm Plan Check | 10/14/2016 | | 10/14/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/14/2016 | | DONE |
|
|
|
Plan modification approved. No additional plan review comments.
|
INSP-Alarm Testing | 10/12/2016 | 10/13/2016 | 10/13/2016 | A | DONE |
Troy Cobbley
|
|
|
Need to add smoke detector in the Nurses Station area, need to relocate two other smoke detectors away from air diffusers, one wall mount strobe was non-functional, audio was not temporal but march time, elevator recall was not tested or any of the new smoke detectors in the corridor system. Scott Arellano is ok with a 30 day temporary to allow time for the contractor to correct the audio as long as all other items have been corrected.
|
Alarm Plan Check | 6/13/2016 | | 6/13/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/13/2016 | | DONE |
|
|
|
Plan modification approved as noted. No additional review comments.
|
Permit Ready to Issue | | | 6/13/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/13/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/13/2016 | | 6/13/2016 | | DONE |
Candy A. Nichols
|
|
|
|
Miscellaneous action | | | 6/13/2016 | | DONE |
|
|
|
Dante emailed architect's documents that show the bathroom as non functional so weatherproof notification will not be required. The game room also has an area noted as requiring coverage but the furniture layout shows that this is not space that can be occupied so visual notification not needed.
|
Miscellaneous action | | | 6/9/2016 | | DONE |
|
|
|
Project reopened for plan modification at vendor's request.
|
CHANGE STATUS TO (REV) | | | 6/9/2016 | | DONE |
|
|
|
Reopened for plan modification
|
1st review completed | | | 6/1/2016 | | PASS |
|
|
|
|
Alarm Plan Check | 6/1/2016 | | 6/1/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/1/2016 | | DONE |
|
|
|
Plans approved as noted with review comments.
|
Permit Ready to Issue | | | 6/1/2016 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 6/1/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/1/2016 | | 6/1/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Application received | | | 5/26/2016 | | DONE |
|
|
|
Application submitted via PDS Online on May 26 2016 10:35AM
|
Plan assigned to (Lee) | 5/26/2016 | | 5/26/2016 | | DONE |
Lee G Meredith
|
|
|
|