INSP-Final Inspection | 7/11/2016 | 7/12/2016 | 7/12/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in | 7/11/2016 | 7/12/2016 | 7/12/2016 | P | PASS |
Jim Page
|
|
|
Overhead fire sprinkler piping rough in inspection complete.
|
Sprinkler Plan Check | 6/9/2016 | | 6/9/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/9/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/9/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/9/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/9/2016 | | 6/9/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 6/8/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/8/2016 | | 6/8/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/8/2016 | | 6/8/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 6/8/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/8/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 6/6/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 6 2016 9:15AM
|