INSP-Final Inspection | 1/30/2017 | 2/2/2017 | 2/2/2017 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection passed/complete
|
INSP-Final Inspection | 1/13/2017 | 1/13/2017 | 1/13/2017 | A | PART |
Jim Page
|
|
|
Final fire alarm inspection comlete for area's requested for TCO (levels 1 through 4, active fire alarm inspection complete for level 5 corridors as well as sprinkler monitoring for entire building)
|
Miscellaneous action | | | 10/21/2016 | | DONE |
|
|
|
Duct detector product data received.
|
Alarm Plan Check | 10/21/2016 | | 10/21/2016 | | PASS |
Lee G Meredith
|
|
|
Approved as noted. Fan monitoring and control not show. This information is to be provided on as built drawings prior to final acceptance and meet the requirements of 2012 IFC, as noted on drawings and review comments.
|
PLANS TAKEN FRONT DESK ALARM | | | 10/21/2016 | | DONE |
|
|
|
Plan modufication submittal approved with review comments and requirements noted on drawings.
|
Telephone call | | | 10/21/2016 | | DONE |
|
|
|
Ken called to say that he will be adding temperature monitoring to a garage interstitial space and wanted to know if resubmittal was required. I informed him that it would.
|
CHANGE STATUS TO (ISS) | | | 10/21/2016 | | DONE |
|
|
|
|
Miscellaneous action | | | 10/19/2016 | | |
|
|
|
Traditional duct detector product data missing. Contacted Rita and Ken to request they send me the information.
|
Plan Modification Accepted | | | 10/18/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (REV) | | | 10/18/2016 | | DONE |
|
|
|
|
Miscellaneous action | | | 10/18/2016 | | DONE |
|
|
|
Revised drawings show in-duct detectors for fire smoke dampers. ESI indicated standard duct detectors would be used. Emailed Ken to confirm which is correct.
|
Miscellaneous action | | | 10/11/2016 | | DONE |
|
|
|
Rita Doty uploaded a resubmittal of this project under a new permit number. After confirming this with her, I informed her that she would need to contact the permit desk to cancel the new permit and I would reopen this project so she could upload the resubmittal into the correct project.
|
Miscellaneous action | | | 8/19/2016 | | DONE |
|
|
|
Ken emailed a request to allow heat detection in suite bathrooms to be allowed as an alternate to in duct smoke detectors for fire smoke dampers. I responded that they could not because of the smoke rating and because the fire rating already requires internal heat activation of the damper so it would be redundant.
|
Permit Ready to Issue | | | 8/10/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/10/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/10/2016 | | 8/10/2016 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 8/9/2016 | | DONE |
|
|
|
Returned a call to Ken. He did not see the need for the page microphone at the annunciator. I quoted 2012 IFC 907.6.3.1 which states the zone indicator panel is to have associated controls. Ken asked if the fire alarm panel could be moved to the lobby and the remote annunciator removed. I told him this was acceptable. THis shall be noted on the approved drawing.
|
Alarm Plan Check | 8/9/2016 | | 8/9/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/9/2016 | | DONE |
|
|
|
Plans approved with review comments and requirements.
|
Miscellaneous action | | | 8/4/2016 | | DONE |
|
|
|
Drawing FA 0.2.2 received that includes all speaker calculations.
|
Miscellaneous action | | | 8/4/2016 | | DONE |
|
|
|
Also requested updated product data and calcs that include primary and remote page microphones that currently aren't shown.
|
Miscellaneous action | | | 8/3/2016 | | DONE |
|
|
|
Missing calculations for speaker circuits S5 - S8. Emailed Rita requesting she email them to me so I can insert them. Review to continue once received.
|
Plan resubmittals received | | | 8/2/2016 | | DONE |
|
|
|
|
Miscellaneous action | | | 7/20/2016 | | DONE |
|
|
|
Ken emailed to indicate in duct detectors should not be required for the fire smoke dampers that enter into the suites since he has provided full coverage (IMC 607.3.3.2(5)). I informed him taht 1/2 of the dampers served only the bathrooms, which aren't covered by suite detection. Also, in some suites, detector spacing has been exceeded and also cannot be considered full coverage.
|
Miscellaneous action | | | 7/11/2016 | | DONE |
|
|
|
Ken left a voice message regarding my review comment request for more detail on the fire smoke dampers. I emailed a response to let him know that I reviewed the approved mechanical drawings and confirmed that smoke detection is required at all of the locations Ken has noted on his shop drawings.
|
CHANGE STATUS TO (REV) | | | 7/8/2016 | | DONE |
|
|
|
|
Alarm Plan Check | 7/8/2016 | | 7/8/2016 | | FAIL |
Lee G Meredith
|
|
|
See 2nd review comments.
|
Miscellaneous action | | | 7/8/2016 | | DONE |
|
|
|
2nd review comments sent to Ken Webster via email.
|
Plan resubmittals received | | | 7/7/2016 | | DONE |
|
|
|
|
Telephone call | | | 6/20/2016 | | DONE |
|
|
|
Ken called to ask if standard high rise code would be applied to voice evacuation sequence. I discussed this with Time Woodard. He and I agreed that general evac would be adequate since voice evac was required as part of the aerial access and not based on occupant load. I emailed this info to Ken.
|
Telephone call | | | 6/10/2016 | | DONE |
|
|
|
Ken called for clarification on high rise design requirements noted in the review comments. He said that the building does not meet the standard requirements of a high rise. I informed him that there is an alternate design document that was submitted by the architect with high rise provisions which was approved in September of 2015. I emailed him a copy for reference. The approved design alternate included IB construction, NFPA 13 sprinklers, roof access via both stairs, pressurized stairwells, voice evac system, enhanced emergency radio responder coverage, generator and fire pump.
|
Plan assigned to (Lee) | 6/9/2016 | | 6/9/2016 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 6/9/2016 | | FAIL |
|
|
|
See 1st review comments.
|
Miscellaneous action | | | 6/9/2016 | | DONE |
|
|
|
Emailed review comments to Ken Webster.
|
Application received | | | 6/7/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 7 2016 2:52PM
|