INSP-Final Inspection | 3/7/2017 | 3/7/2017 | 3/7/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 11/15/2016 | 11/15/2016 | 11/15/2016 | P | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for level 5 and greenhouse of annex complete. FIR permit will stay in issued status (Partial final for records) until BLD permit is ready to be finaled on life fire safety, at time of life fire safety completion FIR permit will be finaled as well.
|
Permit Ready to Issue | | | 7/11/2016 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 7/11/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/11/2016 | | 7/11/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Sprinkler Plan Check | 7/6/2016 | | 7/6/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 7/6/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/6/2016 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 6/22/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/22/2016 | | 6/22/2016 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/22/2016 | | PEND |
|
|
|
Waiting on a letter from a PE verifying the green house framing is capable of supporting the water filled piping plus 250#
|
Application received | | | 6/20/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 20 2016 4:09PM
|