INSP-Final Inspection | 10/10/2016 | 10/10/2016 | 10/10/2016 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 10/6/2016 | 10/7/2016 | 10/7/2016 | A | FAIL |
Troy Cobbley
|
|
|
Need to secure the poly piping in the crawl space every 32" as discussed. The cpvc risers need to be with-in 1 1/2" of the wall as per available listing. Provide fire caulking in the closets as discussed.
|
INSP-Final Inspection | 9/23/2016 | 9/26/2016 | 9/26/2016 | P | CANC |
Troy Cobbley
|
|
|
Project is not ready for a final yet due to fire alarm not being installed yet.
|
INSP-Sprinkler Rough-in/Hydro | 8/4/2016 | 8/4/2016 | 8/4/2016 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 7/28/2016 | 8/1/2016 | 8/1/2016 | P | PASS |
Troy Cobbley
|
|
|
Overhead rough-in and tenting passed. Piping can be covered.
|
INSP-Supply line flush | 7/28/2016 | 8/1/2016 | 7/28/2016 | A | CANC |
Troy Cobbley
|
|
|
Colton is the contact. Thanks. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
Permit Ready to Issue | | | 6/28/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/28/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/28/2016 | | 6/28/2016 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 6/27/2016 | | PASS |
|
|
|
|
Plan assigned to (Lee) | 6/27/2016 | | 6/27/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/27/2016 | | 6/27/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 6/27/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 6/25/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 25 2016 10:41AM
|