INSP-Final Inspection | 10/30/2017 | 10/31/2017 | 10/31/2017 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 10/25/2017 | 10/27/2017 | 10/27/2017 | A | CANC |
Troy Cobbley
|
|
|
Bob Thorton will be the site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker
|
CHANGE STATUS TO (ISS) | | | 10/27/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/27/2017 | | DONE |
|
|
|
|
INSP-Final Inspection | 10/25/2017 | 10/26/2017 | 10/26/2017 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for final yet but we did test two of the three fire smoke dampers and the dry pipe system interconnects. Still waiting on plan modifications, elevator and fire doors.
|
Plan Modification Accepted | | | 10/26/2017 | | DONE |
|
|
|
|
Alarm Plan Check | 10/26/2017 | | 10/26/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/26/2017 | | DONE |
|
|
|
Plan mod approved. No additional review comments. All changes to be verified by field inspector.
|
Permit Ready to Issue | | | 10/26/2017 | | DONE |
|
|
|
Plan Mod Approved, DO NOT REISSUE
|
INSP-Alarm Testing | 10/25/2017 | 10/25/2017 | 10/25/2017 | P | DONE |
Troy Cobbley
|
|
|
See the on site as-builts for devices marked "ok" that have been tested.
|
INSP-Alarm Testing | 10/18/2017 | 10/19/2017 | 10/19/2017 | A | DONE |
Troy Cobbley
|
|
|
For todays inspection I witnessed the corrections for the notification devices and verified sync. and that all notification devices were functional. No initiating devices have been tested. Not all access has been provided for the fire/smoke dampers and not all of the fire sprinkler devices have been connected and pre-tested yet.
|
INSP-Alarm Testing | 10/17/2017 | 10/18/2017 | 10/18/2017 | P | DONE |
Troy Cobbley
|
|
|
We set off the alarms and it mistakenly set off the alarms and shunted the elevator in the ajoining building. Testing was stopped and agreed to reschedule for tomorrow morning.
Phone #: ###-#### Inspection requested via web by Stacie Tasker
|
Miscellaneous action | | | 10/18/2017 | | DONE |
|
|
|
As built drawings received.
|
INSP-Final Inspection | 10/17/2017 | 10/17/2017 | 10/17/2017 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was an initial walk through. I noted that there are two missing horn/strobes in the basement (and a room), one strobe in the basement has been set at 110cd instead of 75cd as shown on the plans, first floor horn/strobes in the south building are incorrectly set at 75cd instead of 15cd, the south building second floor horn/strobe is located too far from the end of the corridor, not all of the fire/smoke dampers have been provided access for verification of correct closure, none of the elevator fire doors are installed, need map, basement manual pull station is mounted too high. We set off the horn, strobes and found that nothing is sync'ing as required by NFPA 72. As-builts are needed showing the changes and will need to be approved by the engineer of record. No actual testing of devices was performed at this time.
Greg Phone #: ###-####
|
Alarm Plan Check | 8/1/2016 | | 8/1/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/1/2016 | | PASS |
|
|
|
Plans approved with review comments and requirements.
|
Issue and Print Permit | | | 8/1/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/1/2016 | | 8/1/2016 | | DONE |
Brittany Hill
|
|
|
|
(F) Reprint permit | | | 8/1/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/1/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/12/2016 | | DONE |
|
|
|
New drawings submitted to address failed pre-screen review.
|
1st review completed | | | 7/12/2016 | | FAIL |
|
|
|
See 1st review comments.
|
Plan assigned to (Lee) | 7/7/2016 | | 7/7/2016 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 7/7/2016 | | DONE |
|
|
|
Emailed Mary to let her know that the drawing detail is not clear. Review cannot be done until they are cleaned up. Missing floor plan detail in some areas and excessive detail in others that prevents continuing. Mary indicated that she was not able to get clean drawings from Erstad but upon checking building permit drawings, I found all floor plans to be clear and concise. I informed Mary of this. Submittal returned on pre screen review.
|
Application received | | | 7/6/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 6 2016 4:45PM
|