Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberFIR16-00447
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 3176 S DENVER WAY
Project NameSt. Lukes Central Lab Remodel
Customer Number 
ePlanReviewYes
Description
[St. Luke's - Automation Lab]
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration. Sprinklers will be changed to quick response type.

[BLD16-01530] - Permit is to remodel an existing 2,400 sq. ft. 1st floor space area within a 36,625 sq. ft. building. Approval is contingent upon adhering to the approved plans on file. Work to include: removal of select wall for new door opening, construction of select interior nonbearing walls to create an office and a dark room, furring out existing columns, new millwork, new suspended acoustic ceiling, new light fixtures, electrical work, new sinks, plumbing work, mechanical work and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/22/20168/22/20168/22/2016PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete
INSP-Sprinkler Rough-in8/19/20168/22/20168/22/2016APASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping complete, overhead fire sprinkler piping associated with this area of work approved for cover.
Permit Ready to Issue  7/11/2016 DONE
all requirments met
Issue and Print Permit  7/11/2016 DONE
Inspection Record Card- Fire7/11/2016 7/11/2016 DONE
DetailsCarlos Velazquez
(F) Reprint permit  7/11/2016 DONE
Intake Approval  7/8/2016 PASS
Plan assigned to (Tim)7/8/2016 7/8/2016 DONE
DetailsTim Frost
Sprinkler Plan Check7/8/2016 7/8/2016 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  7/8/2016 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  7/8/2016 DONE
DetailsTim Frost
Application received  7/7/2016 DONE
Application submitted via PDS Online on Jul 7 2016 6:27PM