INSP-Final Inspection | 7/25/2017 | 7/26/2017 | 7/25/2017 | A | PASS |
Jim Page
|
|
|
Final inspection for underground supply passed/complete
|
INSP-Sprinkler Rough-in | 7/26/2016 | 7/28/2016 | 7/28/2016 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, underground supply approved for cover.
|
Application received | | | 7/11/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 11 2016 1:49PM
|
Plan assigned to (Scott) | 7/11/2016 | | 7/11/2016 | | PASS |
Scott Arellano
|
|
|
|
Sprinkler Plan Check | 7/11/2016 | | 7/11/2016 | | PASS |
Scott Arellano
|
|
|
Plans are approved as shown. Depth of bury shall be 4 feet 6 inches from top of pipe to finished grade. Final approval is subject to satisfactory field inspection by the PDS/Fire inspector.
|
1st review completed | | | 7/11/2016 | | PASS |
|
|
|
|
Permit Ready to Issue | | | 7/11/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/11/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/11/2016 | | 7/11/2016 | | DONE |
Candy A. Nichols
|
|
|
|