INSP-Final Inspection | 4/27/2017 | 4/28/2017 | 4/28/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 4/26/2017 | 4/27/2017 | 4/27/2017 | P | FAIL |
Troy Cobbley
|
|
|
Horns do not sync as required
|
Miscellaneous action | | | 4/27/2017 | | DONE |
|
|
|
As built drawings received showing sprinkler riser tamper corrections. Accepted and inserted in to electronic plans.
|
INSP-Final Inspection | 4/25/2017 | 4/26/2017 | 4/26/2017 | A | FAIL |
Troy Cobbley
|
|
|
Started inspection but found that the elevator recall did not function and panel was constantly in Trouble due to people trying to fix things so I stopped the inspection. Will need to start from beginning. Need review comments.
|
INSP-Final Inspection | 4/21/2017 | 4/24/2017 | 4/24/2017 | P | CANC |
Troy Cobbley
|
|
|
No fire alarm test due to the sprinkler contractor not having water turned on and elevator guy was not there.
|
Miscellaneous action | | | 4/18/2017 | | DONE |
|
|
|
Received as built drawings with GSM communicator substituted for originally planned dialer.
|
Miscellaneous action | | | 7/26/2016 | | DONE |
|
|
|
Rob requested workflow be re-opened due to product change.
|
Plan Modification Accepted | | | 7/26/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (REV) | | | 7/26/2016 | | DONE |
|
|
|
Plan mod due to product change.
|
1st review completed | | | 7/26/2016 | | PASS |
|
|
|
|
Alarm Plan Check | 7/26/2016 | | 7/26/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 7/26/2016 | | DONE |
|
|
|
Plan modification approved. No additional review comments.
|
CHANGE STATUS TO (ISS) | | | 7/26/2016 | | DONE |
|
|
|
Plan Mod. No fees due per Lee M
|
Permit Ready to Issue | | | 7/15/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/15/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/15/2016 | | 7/15/2016 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 7/14/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 14 2016 10:25AM
|
Plan assigned to (Lee) | 7/14/2016 | | 7/14/2016 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 7/14/2016 | | PASS |
|
|
|
|
Alarm Plan Check | 7/14/2016 | | 7/14/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 7/14/2016 | | DONE |
|
|
|
Plans approved with review comments.
|