INSP-Final Inspection | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Supply line flush | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in/Hydro | 11/4/2016 | 11/7/2016 | 11/7/2016 | A | FAIL |
Troy Cobbley
|
|
|
Underground hydro test failed due to visible loss on guage.
|
INSP-Sprinkler Rough-in/Hydro | 11/2/2016 | 11/2/2016 | 11/2/2016 | P | FAIL |
Troy Cobbley
|
|
|
Underground hydro test failed because when I came back to verify pressure some one had removed the guage. So no test was performed.
|
INSP-Sprinkler Rough-in | 8/4/2016 | 8/5/2016 | 8/5/2016 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground supply piping is ok for cover.
|
INSP-Sprinkler Rough-in | 7/20/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Troy Cobbley
|
|
|
Todays inspection was just for the underground stub-out to 5'-0". It is ok for cover. We spoke about the CPVC requirment to be with-in 1 1/2" of the wall when exposed.
|
Issue and Print Permit | | | 7/15/2016 | | DONE |
|
|
|
|
Application received | | | 7/14/2016 | | |
|
|
|
|
Plan assigned to (Scott) | 7/14/2016 | | 7/14/2016 | | PASS |
Scott Arellano
|
|
|
No separate comments attached to plans. Plans approved as noted.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/14/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/14/2016 | | DONE |
|
|
|
All Met
|
Inspection Record Card- Fire | 7/14/2016 | | 7/14/2016 | | DONE |
Brittany Hill
|
|
|
|
Telephone call | | | 7/14/2016 | | DONE |
|
|
|
Spoke with Ron informing him this permit is ready and the fee amount that is due
|