Permit NumberFIR16-00461
StatusFinaled
Name AMERICAN FIRE PROTECTION LLC
Site Address 590 E BOISE AVE
Project NameAsian Cuisine TI
Customer Number 
ePlanReviewYes
Description
[Asian Cuisine TI]
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration.

[BLD16-02004] - The fire sprinkler system is used for building area increase and for fire area. To remodel an existing 2,531 square foot restaurant for a new restaurant tenant. Work is to include interior nonbearing walls, millwork, finishes, and kitchen equipment. The restrooms are required to be maintained accessible to the disabled as defined by the code in effect when they were created. The existing grease hood (Type I) will be reused. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. A separate fire sprinkler permit shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/12/201610/12/201610/12/2016PPASS
DetailsJim Page
Final fire sprinkler inspection passed/complete.
INSP-Final Inspection8/9/20168/9/20168/9/2016PCANC
DetailsJim Page
Scope of work overhead fire sprinkler piping not ready for final inspection. Overhead fire sprinkler final inspection will need to be accomplished close to the finish stage of tenant space.
INSP-Sprinkler Rough-in8/9/20168/9/20168/9/2016PCANC
DetailsJim Page
Rough to cover inspection completed, this inspection request cancelled.
INSP-Final Inspection8/8/20168/9/20168/9/2016ACANC
DetailsJim Page
Scope of work overhead fire sprinkler piping not ready for final inspection. Overhead fire sprinkler final inspection will need to be accomplished close to the finish stage of tenant space.
INSP-Sprinkler Rough-in8/8/20168/9/20168/9/2016APASS
DetailsJim Page
Rough to cover inspection for scope of work complete for overhead fire sprinkler piping, scope of work overhead fire sprinkler piping approved for cover
Issue and Print Permit  7/26/2016 DONE
Inspection Record Card- Fire7/26/2016 7/26/2016 DONE
DetailsBrittany Hill
Intake Approval  7/20/2016 PASS
Plan assigned to (Tim)7/20/2016 7/20/2016 DONE
DetailsTim Frost
Sprinkler Plan Check7/20/2016 7/20/2016 FAIL
DetailsTim Frost
Please, see attached comments.
1st review completed  7/20/2016 FAIL
DetailsTim Frost
Miscellaneous action  7/20/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  7/15/2016 DONE