Permit Information
Permit NumberFIR16-00473
StatusFinaled
Name DELTA FIRE SYSTEMS
Site Address 2950 E PARKCENTER BLVD
Project NameArboretum at Barber Station
Customer NumberUDG ONLY
ePlanReviewYes
Description
[Arboretum at Barber Station - Building #1, #2, #3 - Udg Only]
The fire sprinkler scope of work consists of underground supply to three buildings from a loop main.

[BLD16-01058] - Permit to construct a new 121,503 square foot (5) story apartment building. First floor foundation and concrete podium permit submitted under BLD15-04472. Each floor is approximately 24,176 square feet. Approval contingent upon adhering to the approved plans on file and attached engineering. This building is fully fire sprinklered with an NFPA 13 system to comply with special provisions of section 510.2 and area increase. Scope of work includes: interior finish of the first floor, construction of wood frame 4 story building on top of the previously approved podium, installation of interior non-bearing walls and bearing walls to create 76 individual units, new plumbing, new electrical, new mechanical, new insulation, new windows, new doors, and interior finishes in compliance with Chapter 8 of the 2012 IBC. This building will be sprinklered with special provisions of section 510.2 and area increase. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/1/20185/1/20185/1/2018PPASS
DetailsJim Page
Final underground supply inspection complete.
INSP-Sprinkler Rough-in/Hydro12/4/201712/4/201712/4/2017APASS
DetailsJim Page
Final inspection for fire sprinkler underground supply with buildings 1, 2 and 3 complete.
INSP-Supply line flush6/9/20176/9/20176/9/2017ADONE
DetailsJim Page
Underground supply flush complete for buildings 1, 2 and 3
INSP-Sprinkler Rough-in10/11/201610/11/201610/11/2016PPASS
DetailsJim Page
Hydrostatic test for underground supply complete.
INSP-Sprinkler Rough-in/Hydro10/6/201610/6/201610/6/2016PCANC
DetailsJim Page
Christopher Phone #: ###-####
INSP-Sprinkler Rough-in10/5/201610/5/201610/5/2016PPASS
DetailsJim Page
Underground main supply approved for cover.
INSP-Sprinkler Rough-in/Hydro10/3/201610/3/201610/3/2016PPASS
DetailsJim Page
200 psi hydrostatic test for underground supply complete.
INSP-Sprinkler Rough-in9/1/20169/2/20169/2/2016APASS
DetailsJim Page
Rough to cover inspection for building 1 fire sprinkler supply underground piping complete, fire sprinkler supply underground piping for building 1 approved for cover.
INSP-Sprinkler Rough-in/Hydro8/11/20168/12/20168/12/2016APASS
DetailsTroy Cobbley
The underground hydro test for Building #2 passed
INSP-Sprinkler Rough-in8/9/20168/10/20168/10/2016APART
DetailsJim Page
Rough to cover inspection for underground supply for building 2 complete, building 2 underground supply approved for cover.
Override - Parcel Holds8/9/20161/1/19008/9/2016  
fire only
Override - Parcel Holds  8/1/2016  
Permit Ready to Issue  8/1/2016 DONE
Override - Parcel Holds  8/1/2016  
Issue and Print Permit  8/1/2016 DONE
Override - Parcel Holds  8/1/2016  
Inspection Record Card- Fire8/1/2016 8/1/2016 DONE
DetailsChristina Prado
Sprinkler Plan Check7/28/2016 7/28/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  7/28/2016 DONE
DetailsTim Frost
Intake Approval  7/25/2016 PASS
Plan assigned to (Tim)7/25/2016 7/25/2016 DONE
DetailsTim Frost
Sprinkler Plan Check7/25/2016 7/25/2016 FAIL
DetailsTim Frost
1st review completed  7/25/2016 FAIL
DetailsTim Frost
Miscellaneous action  7/25/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  7/21/2016 DONE
Application submitted via PDS Online on Jul 21 2016 10:25AM