INSP-Final Inspection | 2/16/2017 | 2/17/2017 | 2/17/2017 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 2/13/2017 | 2/13/2017 | 2/13/2017 | P | PASS |
Jim Page
|
|
|
Hydrostatic test for dry system complete
|
INSP-Sprinkler Rough-in | 1/11/2017 | 1/11/2017 | 1/11/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/pendant fire sprinkler heads located in the ceiling grid area's complete, overhead fire sprinkler piping in ceiling grid area's approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 1/9/2017 | 1/10/2017 | 1/10/2017 | A | PASS |
Jim Page
|
|
|
24 hour air test for dry system complete
|
INSP-Sprinkler Rough-in/Hydro | 1/6/2017 | 1/9/2017 | 1/9/2017 | A | PART |
Jim Page
|
|
|
Hydrostatic test complete for wet system, 24 hour air test started at 9:30AM with 40 PSI.
|
INSP-Sprinkler Rough-in/Hydro | 12/15/2016 | 12/15/2016 | 12/15/2016 | P | PART |
Jim Page
|
|
|
24 dry air system started with 40psi @ 11:00AM. Rough to cover inspection complete for hardlids, cover approved for hardlids.
|
INSP-Supply line flush | 11/28/2016 | 11/29/2016 | 11/29/2016 | A | DONE |
Jim Page
|
|
|
Underground supply line flush complete
|
INSP-Sprinkler Rough-in/Hydro | 11/7/2016 | 11/7/2016 | 11/7/2016 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
Plan Modification Accepted | | | 11/2/2016 | | DONE |
|
|
|
|
Sprinkler Plan Check | 11/2/2016 | | 11/2/2016 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 11/2/2016 | | 11/2/2016 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/2/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/2/2016 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 8/22/2016 | 8/23/2016 | 8/23/2016 | A | PASS |
Jim Page
|
|
|
FInal inspection for underground piping that is installed passed/complete, underground supply approved for cover.
|
INSP-Sprinkler Rough-in | 8/22/2016 | 8/22/2016 | 8/22/2016 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for underground piping installed, thrust block for in building riser will be poured on 23AUG2016, IBR and thrust block will be inspected for rough to cover when complete.
|
Sprinkler Plan Check | 8/2/2016 | | 8/2/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/2/2016 | | DONE |
Tim Frost
|
|
|
|
Issue and Print Permit | | | 8/2/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/2/2016 | | 8/2/2016 | | DONE |
Brittany Hill
|
|
|
|
Intake Approval | | | 8/1/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/1/2016 | | 8/1/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/1/2016 | | 8/1/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 8/1/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 8/1/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 7/29/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 29 2016 9:45AM
|