INSP-Final Inspection | 11/2/2016 | 11/2/2016 | 11/2/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/1/2016 | 11/1/2016 | 11/1/2016 | P | FAIL |
Troy Cobbley
|
|
|
A plan modification is needed to verify that the two extended coverage sprinkler pendants can be used. Also need the missing canopies provided and the three painted/covered upright heads addressed.
|
INSP-Final Inspection | 10/31/2016 | 11/1/2016 | 11/1/2016 | A | FAIL |
Troy Cobbley
|
|
|
I tried calling the contact repeatedly but no answer. Phone would not go to voice mail. I went to project and was unable to make contact. I found ceilings installed in areas without approval. Tile to be removed for inspection.
Richard Clark is the contact for this inspection. Thank you, Phone #: ###-#### Inspection requested via web by Kay Haney
|
INSP-Sprinkler Rough-in | 8/2/2016 | 8/3/2016 | 8/3/2016 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for Restrooms where piping is ok to cover.
|
Intake Approval | | | 8/2/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/2/2016 | | 8/2/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/2/2016 | | 8/2/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 8/2/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/2/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/2/2016 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 8/2/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/2/2016 | | 8/2/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Application received | | | 7/29/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 29 2016 10:02AM
|