INSP-Final Inspection | 4/19/2017 | 4/20/2017 | 4/20/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Supply line flush | 3/27/2017 | 3/28/2017 | 3/28/2017 | P | DONE |
Jim Page
|
|
|
Underground main supply flush completed
|
INSP-Sprinkler Rough-in | 2/23/2017 | 2/23/2017 | 2/23/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for level 2 tenting complete, all overhead fire sprinkler piping for this permit approved for cover
|
INSP-Sprinkler Rough-in/Hydro | 10/12/2016 | 10/13/2016 | 10/13/2016 | P | PART |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping complete for levels 1 and 2. Rough to cover inspection for overhead fire sprinkler piping complete, overhead fire sprinkler piping located on level 1 approved for cover, overhead fire sprinkler piping located on level 2 cannot be covered until tenting inspection is complete. The 2nd level has a balcony that is not on the approved drawings, this balcony is on the southside of the building located on the end, balcony needs a dry sidewall install for coverage, sidewall install will be verified during tenting inspection.
|
Permit Ready to Issue | | | 8/9/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/9/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/9/2016 | | 8/9/2016 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 8/8/2016 | | 8/8/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
Plan resubmittals received | | | 8/8/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/3/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 3 2016 10:40AM
|