INSP-Final Inspection | 5/15/2017 | 5/16/2017 | 5/16/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 5/14/2017 | 5/15/2017 | 5/15/2017 | A | FAIL |
Jim Page
|
|
|
Tamper switches for backflow would not report to panel, all flow switches would not go into alarm with inspectors test.
|
INSP-Final Inspection | 5/11/2017 | 5/12/2017 | 5/12/2017 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for final. Fire alarm contractor was not ready, FDC needs finished, floor needs poured in riser room, riser room needs to be fire caulked, hangers on 2" piping need to be verified as per previous note. Contractor was putting up signage. No actual inspection performed.
|
INSP-Supply line flush | 5/4/2017 | 5/5/2017 | 5/5/2017 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete
|
INSP-Sprinkler Rough-in/Hydro | 3/9/2017 | 3/9/2017 | 3/9/2017 | P | PASS |
Jim Page
|
|
|
3rd Floor hydrostatic test complete
|
INSP-Sprinkler Rough-in/Hydro | 3/7/2017 | 3/8/2017 | 3/8/2017 | P | PART |
Jim Page
|
|
|
Hydro for overhead fire sprinkler piping on levels 1, 2 and 4 complete, level 3 lost pressure, will need to have hydro test completed again for level 3 after repair is made. Rough to cover inspection /tenting inspection complete, all can be covered with exception to the appartment with the 2 inch CPVC suppling the riser from the standpipe/FDC, no hangers were on the 2 inch at time of inspection.
|
INSP-Supply line flush | 3/7/2017 | 3/8/2017 | 3/8/2017 | P | PART |
Jim Page
|
|
|
Inspection request is for underground rough/hydro, not supply line flush. Underground rough to cover inspection complete, underground hydro complete.
|
INSP-Sprinkler Rough-in/Hydro | 3/6/2017 | 3/7/2017 | 3/7/2017 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled by person onsite, Trevor, inspection request will be rescheduled for a later date.
|
INSP-Sprinkler Rough-in | 3/6/2017 | 3/7/2017 | 3/6/2017 | A | CANC |
Jim Page
|
|
|
Tenting inspection. Call Jake when heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2017 | 2/28/2017 | 2/28/2017 | P | CANC |
Jim Page
|
|
|
Not ready for inspection, this request is cancelled.
|
INSP-Sprinkler Rough-in/Hydro | 2/23/2017 | 2/24/2017 | 2/24/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for standpipe complete, approved for cover. Hydrostatic test for standpipe complete.
|
INSP-Sprinkler Rough-in/Hydro | 2/9/2017 | 2/9/2017 | 2/9/2017 | P | FAIL |
Jim Page
|
|
|
Standpipe lost pressure during hydro, will need to be re-tested after repair is made.
|
INSP-Sprinkler Rough-in/Hydro | 2/8/2017 | 2/8/2017 | 2/8/2017 | P | CANC |
Jim Page
|
|
|
Standpipe rough/hydro inspection cancelled per conversation with point of contact, Jake Phone #: ###-####, inspection request will be scheduled for a later date.
|
INSP-Sprinkler Rough-in/Hydro | 1/26/2017 | 1/27/2017 | 1/27/2017 | A | CANC |
Jim Page
|
|
|
Standpipe rough/air test for hydro. Call Jake when heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
Issue and Print Permit | | | 10/21/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/21/2016 | | 10/21/2016 | | DONE |
Brittany Hill
|
|
|
|
Intake Approval | | | 9/2/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 9/2/2016 | | 9/2/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/2/2016 | | 9/2/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 9/2/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/2/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/3/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 3 2016 10:45AM
|